HomeMy WebLinkAbout2026-2035 Capital Budget FINAL SYHAgt
Municipality
Of Bay ham
2026 - 2035
Capital
Budget
Municipality of Bayham
2026-2035 Capital Summary
2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
Expenditures
General Government $50,000 $90,000 $65,000 $40,000 $40,000 $90,000 $40,000 $85,000 $50,000 $90,000
Fire $739,250 $488,500 $447,050 $1,075,000 $393,500 $150,000 $1,100,000 $40,000 $41,000 $27,000
Building $0 $55,000 $0 $0 $0 $0 $0 $0 $0 $0
Public Works $2,098,500 $4,331,500 $4,160,500 $4,731,500 $10,069,500 $7,402,500 $13,709,500 $6,946,500 $5,164,500 $874,000
Water $0 $80,500 $18,197,000 $309,000 $388,000 $437,000 $32,000 $33,000 $72,500 $72,500
Wastewater $656,000 $878,500 $176,000 $17,605,000 $18,075,000 $203,000 $112,000 $217,000 $162,500 $162,500
Parks&Rec. $475,000 $720,000 $380,000 $110,000 $90,000 $90,000 $90,000 $90,000 $90,000 $50,000
Facilities $5,330,250 $185,000 $650,000 $0 $150,000 $25,000 $130,000 $0 $0 $0
Planning&Development $45,000 $25,000 $0 $0 $40,000 $15,000 $35,000 $0 $30,000 $30,000
$9,394,000 $6,854,000 $24,075,550 $23,870,500 $29,246,000 $8,412,500 $15,248,500 $7,411,500 $5,610,500 $1,306,000
Financing
Tax Levy $2,487,750 $3,365,000 $3,352,550 $2,456,500 $5,863,000 $2,507,500 $2,829,500 $1,176,500 $1,675,500 $346,000
Development Charges $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grants $3,274,250 $2,380,000 $19,108,000 $20,644,000 $22,831,000 $5,190,000 $12,020,000 $5,940,000 $3,690,000 $215,000
Reserves $2,203,000 $1,064,000 $1,565,000 $750,000 $552,000 $715,000 $369,000 $295,000 $245,000 $745,000
Other $40,000 $45,000 $50,000 $20,000 $0 $0 $30,000 $0 $0 $0
Debt Financing $1,389,000 $0 $0 $0 $0 $0 $0 $0 $0 $0
$9,394,0001 $6,854,0001 $24,075,5501 $23,870,5001 $29,246,0001 $8,412,5001 $15,248,5001 $7,411,5001 $5,610,5001 $1,306,000
By-law No.2026-Oxx
Schedule'W'
Municipality of Bayham
2026 Capital Summary
Financing
Total Cost I Reserve Fund I DC's Debt Financing Grants I Other I Tax Levy I Page Reference
Expenditures
General Government $50,000 $10,000 $0 $0 $0 $0 $40,000 14
Fire $739,250 $0 $0 $0 $0 $0 $739,250 25
Building $0 $0 $0 $0 $0 $0 $0 36
Public Works $2,098,500 $190,000 $0 $0 $300,000 $40,000 $1,568,500 47
Water $0 $0 $0 $0 $0 $0 $0 58
Wastewater $656,000 $656,000 $0 $0 $0 $0 $0 69
Parks&Rec. $475,000 $410,000 $0 $0 $0 $0 $65,000 80
Facilities $5,330,250 $892,000 $0 $1,389,000 $2,974,250 $0 $75,000 91
Planning&Development $45,000 $45,000 $0 $0 $0 $0 $0 102
$9,394,000 $2,203,000 $0 $1,389,000 $3,274,250 $40,000 $2,487,750
Municipality of Bayham
2027 Capital Summary
Financing
Total Cost I Reserve Fund I DC's I Debt Financing Grants I Other Tax Levy I Page Reference
Expenditures
General Government $90,000 $50,000 $0 $0 $0 $0 $40,000 15
Fire $488,500 $0 $0 $0 $0 $0 $488,500 26
Building $55,000 $55,000 $0 $0 $0 $0 $0 37
Public Works $4,331,500 $0 $0 $0 $2,155,000 $45,000 $2,131,500 48
Water $80,500 $80,500 $0 $0 $0 $0 $0 59
Wastewater $878,500 $878,500 $0 $0 $0 $0 $0 70
Parks&Rec. $720,000 $0 $0 $0 $225,000 $0 $495,000 81
Facilities $185,000 $0 $0 $0 $0 $0 $185,000 92
Planning&Development $25,000 $0 $0 $0 $0 $0 $25,000 103
$6,854,0001 $1,064,0001 $0 $0 $2,380,0001 $45,0001 $3,365,000
Municipality of Bayham
2028 Capital Summary
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Expenditures
General Government $65,000 $25,000 $0 $0 $0 $0 $40,000 16
Fire $447,050 $0 $0 $0 $0 $0 $447,050 27
Building $0 $0 $0 $0 $0 $0 38
Public Works $4,160,500 $0 $0 $0 $1,925,000 $50,000 $2,185,500 49
Water $18,197,000 $1,314,000 $0 $0 $16,883,000 $0 $0 60
Wastewater $176,000 $176,000 $0 $0 $0 $0 $0 71
Parks&Rec. $380,000 $0 $0 $0 $300,000 $0 $80,000 82
Facilities $650,000 $50,000 $0 $0 $0 $0 $600,000 93
Planning &Development $0 $0 $0 $0 $0 $0 $0 104
$24,075,5501 $1,565,000 $0 $0 $19,108,0001 $50,0001 $3,352,550
Municipality of Bayham
2029 Capital Summary
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Expenditures
General Government $40,000 $0 $0 $0 $0 $0 $40,000 17
Fire $1,075,000 $225,000 $0 $0 $0 $0 $850,000 28
Building $0 $0 $0 $0 $0 $0 $0 39
Public Works $4,731,500 $0 $0 $0 $3,165,000 $20,000 $1,546,500 50
Water $309,000 $309,000 $0 $0 $0 $0 $0 61
Wastewater $17,605,000 $216,000 $0 $0 $17,389,000 $0 $0 72
Parks&Rec. $110,000 $0 $0 $0 $90,000 $0 $20,000 83
Facilities $0 $0 $0 $0 $0 $0 $0 94
Planning&Development $0 $0 $0 $0 $0 $0 $0 105
$23,870,5001 $750,000 $0 $0 $20,644,0001 $20,0001 $2,456,500
Municipality of Bayham
2030 Capital Summary
Financing
Total Cost Reserve Fund DC's Debt Financing Grants I Other I Tax Levy I Page Reference
Expenditures
General Government $40,000 $0 $0 $0 $0 $0 $40,000 18
Fire $393,500 $0 $0 $0 $0 $0 $393,500 29
Building $0 $0 $0 $0 $0 $0 $0 40
Public Works $10,069,500 $0 $0 $0 $4,830,000 $0 $5,239,500 51
Water $388,000 $388,000 $0 $0 $0 $0 $0 62
Wastewater $18,075,000 $164,000 $0 $0 $17,911,000 $0 $0 73
Parks&Rec. $90,000 $0 $0 $0 $90,000 $0 $0 84
Facilities $150,000 $0 $0 $0 $0 $0 $150,000 95
Planning&Development $40,000 $0 $0 $0 $0 $0 $40,000 106
$29,246,0001 $552,000 $0 $0 $22,831,0001 $0 $5,863,000
Municipality of Bayham
2031 Capital Summary
Financing
Total Cost IlReserveFund IDC's �Debffinancing Grants Other I Tax Levy I Page Reference
Expenditures
General Government $90,000 $50,000 $0 $0 $0 $0 $40,000 19
Fire $150,000 $0 $0 $0 $0 $0 $150,000 30
Building $0 $0 $0 $0 $0 $0 $0 41
Public Works $7,402,500 $0 $0 $0 $5,100,000 $0 $2,302,500 52
Water $437,000 $437,000 $0 $0 $0 $0 $0 63
Wastewater $203,000 $203,000 $0 $0 $0 $0 $0 74
Parks & Rec. $90,000 $0 $0 $0 $90,000 $0 $0 85
Facilities $25,000 $25,000 $0 $0 $0 $0 $0 96
Planning & Development $15,000 $0 $0 $0 $0 $0 $15,000 107
$8,412,5001 $715,000 $0 $0 $5,190,0001 $0 $2,507,500
Municipality of Bayham
2032 Capital Summary
Financing
Total Cost IlReserveFund IDC's �Debffinancing Grants Other I Tax Levy I Page Reference
Expenditures
General Government $40,000 $0 $0 $0 $0 $0 $40,000 20
Fire $1,100,000 $225,000 $0 $0 $0 $0 $875,000 31
Building $0 $0 $0 $0 $0 $0 $0 42
Public Works $13,709,500 $0 $0 $0 $11,930,000 $30,000 $1,749,500 53
Water $32,000 $32,000 $0 $0 $0 $0 $0 64
Wastewater $112,000 $112,000 $0 $0 $0 $0 $0 75
Parks & Rec. $90,000 $0 $0 $0 $90,000 $0 $0 86
Facilities $130,000 $0 $0 $0 $0 $0 $130,000 97
Planning & Development 1 $35,000 $0 $0 $0 $0 $0 $35,0001 108
$15,248,5001 $369,000 $0 $0 $12,020,0001 $30,0001 $2,829,500
Municipality of Bayham
2033 Capital Summary
Financing
Total Cost IlReserveFund IDC's �Debffinancing Grants Other I Tax Levy I Page Reference
Expenditures
General Government $85,000 $45,000 $0 $0 $0 $0 $40,000 21
Fire $40,000 $0 $0 $0 $0 $0 $40,000 32
Building $0 $0 $0 $0 $0 $0 $0 43
Public Works $6,946,500 $0 $0 $0 $5,850,000 $0 $1,096,500 54
Water $33,000 $33,000 $0 $0 $0 $0 $0 65
Wastewater $217,000 $217,000 $0 $0 $0 $0 $0 76
Parks & Rec. $90,000 $0 $0 $0 $90,000 $0 $0 87
Facilities $0 $0 $0 $0 $0 $0 $0 98
Planning & Development $0 $0 $0 $0 $0 $0 $0 109
$7,411,5001 $295,000 $0 $0 $5,940,0001 $0 $1,176,500
Municipality of Bayham
2034 Capital Summary
Financing
Total Cost IlReserveFund IDC's �Debffinancing Grants Other I Tax Levy I Page Reference
Expenditures
General Government $50,000 $10,000 $0 $0 $0 $0 $40,000 22
Fire $41,000 $0 $0 $0 $0 $0 $41,000 33
Building $0 $0 $0 $0 $0 $0 $0 44
Public Works $5,164,500 $0 $0 $0 $3,600,000 $0 $1,564,500 55
Water $72,500 $72,500 $0 $0 $0 $0 $0 66
Wastewater $162,500 $162,500 $0 $0 $0 $0 $0 77
Parks & Rec. $90,000 $0 $0 $0 $90,000 $0 $0 88
Facilities $0 $0 $0 $0 $0 $0 $0 99
Planning & Development $30,000 $0 $0 $0 $0 $0 $30,000 110
$5,610,5001 $245,000 $0 $0 $3,690,0001 $0 $1,675,500
Municipality of Bayham
2035 Capital Summary
Financing
Total Cost IlReserveFund IDC's �Debffinancing Grants Other I Tax Levy I Page Reference
Expenditures
General Government $90,000 $50,000 $0 $0 $0 $0 $40,000 23
Fire $27,000 $0 $0 $0 $0 $0 $27,000 34
Building $0 $0 $0 $0 $0 $0 $0 45
Public Works $874,000 $460,000 $0 $0 $215,000 $0 $199,000 56
Water $72,500 $72,500 $0 $0 $0 $0 $0 67
Wastewater $162,500 $162,500 $0 $0 $0 $0 $0 78
Parks & Rec. $50,000 $0 $0 $0 $0 $0 $50,000 89
Facilities $0 $0 $0 $0 $0 $0 $0 100
Planning & Development $30,000 $0 $0 $0 $0 $0 $30,000 111
$1,306,0001 $745,000 $0 $0 $215,000 $0 $346,000
Municipality of Bayham
General Government 2026-2035
2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
Expenditures
General Government $50,0001 $90,0001 $65,0001 $40,0001 $40,0001 $90,000 $40,000 $85,000 $50,000 $90,000
$5010001 $90,0001 $65,0001 $40,0001 $40,0001 $90,0001 $40,000 $85,000 $50,000 $90,000
Financing
Tax Levy $40,000 $40,000 $40,000 $40,000 $40,000 $40,000 $40,000 $40,000 $40,000 $40,000
Development Charges $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0 $0 $01 0
Reserves $10,0001 $50,0001 $25,000 $0 $0 $50,0001 $0 $45,0001 $10,000 $50,000
$50YO001 $90,0001 $65,0001 $40,0001 $40,0001 $90,0001 $40,000 $85,0001 $50,0001 $90,000
Municipality of Bayham
General Government-2026
Financing
Total Cost Reserve Fund I DC's Debt Financing Grants Other I Tax Levy
Expenditures
General Government $50,0001 $10,000 $0 $0 $0 $0 $40,000
$50,0001 $10,000 $0 $0 $0 $0 $40,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Council Computers GG-03 $10,000 $10,000 $0 $0 $0 $0 $0 114
Liability Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Working Capital Transfer N/A $10,000 $0 $0 $0 $0 $0 $10,000 N/A
Election Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
$50,000 $10,000 $0 $01 $0 $0 $40,000
Budgeted Reserve Balance
Acc No. Acc.Name Opening Balance Transfer to Transfer from Closing Balance
2301 Working Capital Reserve $124,481 $10,000 $10,000 $124,481
2327 Election Reserve $45,000 $15,000 $60,000 $0
2331 Rate Stablization Reserve $422,138 $15,000 $90,315 $346,823
Municipality of Bayham
General Government-2027
Financing
Total Cost Reserve Fund I DC's Debt Financing Grants Other I Tax Levy
Expenditures
General Government $90,0001 $50,000 $0 $0 $0 $0 $40,000
$90,0001 $50,000 $0 $0 $0 $0 $40,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Market Analysis GG-01 $20,000 $20,000 $0 $0 $0 $0 $0 112
Strategic Plan Update GG-02 $30,000 $30,000 $0 $0 $0 $0 $0 113
Liability Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Working Capital Transfer N/A $10,000 $0 $0 $0 $0 $0 $10,000 N/A
Election Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
$90,000 $50,000 $0 $0 $0 $0 $40,000
Budgeted Reserve Balance Closing
Acc No. Acc. Name Opening Balance Transfer to Transfer from Balance
2301 Working Capital Reserve $124,481 $10,000 $20,000 $114,481
2327 Election Reserve $0 $15,000 $0 $15,000
2331 Rate Stablization Reserve $346,823 $15,000 $30,000 $331,823
Municipality of Bayham
or General Government-2028
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other I Tax Levy
Expenditures
General Government $65,000 $25,000 $0 $0 $0 $0 $40,000
$65,000 $25,000 $0 $0 $0 $0 $405000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Liability Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Workinq Capital Transfer N/A $10,000 $0 $0 $0 $0 $0 $10,000 N/A
Election Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Website Update GG-04 $25,000 $25,000 $0 $0 $0 $0 $0 115
$65,000 $25,000 $0 $0 $0 $0 $40,000
Budgeted Reserve Balance Closing
Acc No. Acc. Name Opening Balance Transfer to Transfer from Balance
2301 Working Capital Reserve $114,481 $10,000 $25,000 $99,481
2327 Election Reserve $15,000 $15,000 $0 $30,000
2331 Rate Stablization Reserve $331,823 $15,000 $0 $346,823
Municipality of Bayham
General Government-2029
Financing
Total Cost I Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
General Government $40,000 $0 $0 $0 $0 $0 $40,000
$40,000 $0 $0 $0 $0 $0 $40,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Liability Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Working Capital Transfer N/A $10,000 $0 $0 $0 $0 $0 $10,000 N/A
Election Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
$40,000 $0 $0 $0 $0 $0 $40,000
Budgeted Reserve Balance Closing
Acc No. Acc. Name Opening Balance Transfer to Transfer from Balance
2301 Working Capital Reserve $99,481 $10,000 $0 $109,481
2327 Election Reserve $30,000 $15,000 $0 $45,000
2331 Rate Stablization Reserve $346,8231 $15,000 $0 $361,823
Municipality of Bayham
General Government-2030
Financing
Total Cost Reserve Fund I DC's Debt Financing Grants Other I Tax Levy
Expenditures
General Government $40,000 $0 $0 $0 $0 $0 $40,000
$40,000 $0 $0 $0 $0 $0 $40,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Council Computers GG-03 $10,000 $10,000 $0 $0 $0 $0 $0 114
Development Charges Review GG-05 $25,000 $25,000 $0 $0 $0 $0 $0 116
Liability Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Working Capital Transfer N/A $10,000 $0 $0 $0 $0 $0 $10,000 N/A
Election Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
$40,000 $0 $0 $0 $0 $0 $40,000
Budgeted Reserve Balance Closing
Acc No. Acc.Name Opening Balance Transfer to Transfer from Balance
2301 Working Capital Reserve $109,481 $10,000 $35,000 $84,481
2327 Election Reserve $45,000 $15,000 $60,000 $0
2331 Rate Stablization Reserve $361,823 $15,000 $0 $376,823
Municipality of Bayham
General Government-2031
Financing
t Reserve Fund I DC's Debt Financing Grants Other I Tax Levy
Expenditures
General Government $90,0001 $50,000 $0 $0 $0 $0 $40,000
$90,0001 $50,000 $0 $0 $0 $0 $40,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Liability Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Market Analysis GG-01 $20,000 $20,000 $0 $0 $0 $0 $0 112
Strategic Plan Update GG-02 $30,000 $30,000 $0 $0 $0 $0 $0 113
Workinci Capital Transfer N/A $10,000 $0 $0 $0 $0 $0 $10,000 N/A
Election Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
$90,000 $50,000 $0 $0 $0 $0 $40,000
Budgeted Reserve Balance Closing
Acc No. Acc.Name Opening Balance Transfer to Transfer from Balance
2301 Working Capital Reserve $84,481 $10,000 $20,0001 $74,481
2327 Election Reserve $0 $15,000 $0 $15,000
2331 Rate Stablization Reserve $376,823 $15,000 $30,0001 $361,823
Municipality of Bayham
General Government-2032
Financing
t Reserve Fund I DC's Debt Financing Grants Other I Tax Levy
Expenditures
General Government $40,000 $0 $0 $0 $0 $0 $40,000
$40,000 $0 $0 $0 $0 $0 $40,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Working Capital Transfer N/A $10,000 $0 $0 $0 $0 $0 $10,000 N/A
Election Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Liability Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
$40,000 $0 $0 $0 $0 $0 $40,000
Budgeted Reserve Balance Closing
Acc No. Acc.Name Opening Balance Transfer to Transfer from Balance
2301 Working Capital Reserve $74,481 $10,000 $0 $84,481
2327 Election Reserve $15,000 $15,000 $0 $30,000
2331 Rate Stablization Reserve $361,823 $15,000 $0 $376,823
Municipality of Bayham
General Government-2033
Financing
t Reserve Fund I DC's Debt Financing Grants Other I Tax Levy
Expenditures
General Government $85,0001 $45,000 $0 $0 $0 $0 $40,000
$85,0001 $45,000 $0 $0 $0 $0 $40,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Working Capital Transfer N/A $10,000 $0 $0 $0 $0 $0 $10,000 N/A
Market Analysis GG-01 $20,000 $20,000 $0 $0 $0 $0 $0 112
Website Update GG-04 $25,000 $25,000 $0 $0 $0 $0 $0 115
Election Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Liability Reserve Transfer I N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
$85,000 $45,000 $0 $01 $0 $0 $40,000
Budgeted Reserve Balance Closing
Acc No. Acc.Name Opening Balance Transfer to Transfer from Balance
2301 Working Capital Reserve $84,481 $10,000 $45,000 $49,481
2327 Election Reserve $30,000 $15,000 $0 $45,000
2331 Rate Stablization Reserve $376,823 $15,000 $0 $391,823
Municipality of Bayham
General Government-2034
Financing
t Reserve Fund I DC's Debt Financing Grants Other I Tax Levy
Expenditures
General Government $50,0001 $10,000 $0 $0 $0 $0 $40,000
$50,0001 $10,000 $0 $0 $0 $0 $40,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Council Computers GG-03 $10,000 $10,000 $0 $0 $0 $0 $0 114
Working Capital Transfer N/A $10,000 $0 $0 $0 $0 $0 $10,000 N/A
Election Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Liability Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
$0 $0 $0 $0 $0 $0 $0
$50,000 $10,000 $0 $0 $0 $0 $40,000
Budgeted Reserve Balance Closing
Acc No. Acc.Name Opening Balance Transfer to Transfer from Balance
2301 Working Capital Reserve $49,481 $10,000 $0 $59,481
2327 Election Reserve $45,000 $15,0001 $60,000 $0
2331 Rate Stablization Reserve $391,823 $15,000 $0 $406,823
Municipality of Bayham
General Government-2035
Financing
t Reserve Fund I DC's Debt Financing Grants Other I Tax Levy
Expenditures
General Government $90,0001 $50,000 $0 $0 $0 $0 $40,000
$90,0001 $50,000 $0 $0 $0 $0 $40,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Market Analysis GG-01 $20,000 $20,000 $0 $0 $0 $0 $0 112
Strategic Plan Update GG-02 $30,000 $30,000 $0 $0 $0 $0 $0 113
Working Capital Transfer N/A $10,000 $0 $0 $0 $0 $0 $10,000 N/A
Election Reserve Transfer N/A $15,000 $0 $0 $0 $0 $0 $15,000 N/A
Liability Reserve Transfer N/A 1 $15,000 $0 $0 $0 $0 $0 $15,000 N/A
$90,000 $50,000 $0 $0 $0 $0 $40,000
Budgeted Reserve Balance Closing
Acc No. Acc.Name Opening Balance Transfer to Transfer from Balance
2301 Working Capital Reserve $59,481 $10,000 $0 $69,481
2327 Election Reserve $0 $15,000 $0 $15,000
2331 Rate Stablization Reserve $406,823 $15,000 $0 $421,823
Municipality of Bayham
Fire 2026-2035 P I
2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
Expenditures
Fire $739,250 $488,5001 $447,0501 $1,075,0001 $393,5001 $150,000 $1,100,000 $40,000 $41,000 $27,000
$739,2501 $488,5001 $447,0501 $1,07590001 $393,5001 $150,000 $1,100,000 $40,000 $41,000 $27,000
Financing
Tax Levy $739,250 $488,500 $447,050 $850,000 $393,500 $150,000 $875,000 $40,000 $41,000 $27,000
Development Charges $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $225,000 $0 $0 $225,000 $0 $0 $0
$739,2501 $488,5001 $447,0501 $19075,000 $393,500 $150,000 $1,100,0001 $40,0001 $41,000 $27,000
Municipality of Bayham
Fire -2026
Financing
Total Cost Reserve Fund DC's �Debffinancing Grants Other Tax Levy
Expenditures
Fire $739,250 $0 $01 $01 $01 $0 $739,250
$739,250 $0 $0 $0 $0 $0 $739,250
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Fire Equipment Reserve Transfer N/A $0 $0 $0 $0 $0 $0 $0 N/A
Bunker Gear FD-01 $16,000 $0 $0 $0 $0 $0 $16,000 117
Tanker 1 Replacement FD-06 $680,000 $0 $0 $0 $0 $0 $680,000 122
Radio System Reseve FD-10 $30,000 $0 $0 $0 $0 $0 $30,000 126
Thermal Imaging Cameras FD-03 $7,250 $0 $0 $0 $0 $0 $7,250 119
Portable Radios FD-02 $6,000 $0 $0 $0 $0 $0 $6,000 118
$739,250 $0 $0 $0 $0 $0 $739,250
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2308 Fire Equipment Reserve $0 $0 $0 $0
2303 Fire Department Apparatus $5,000 $0 $0 $5,000
2375 Fire Radio Reserve $90,000 $30,000 $0 $120,000
Municipality of Bayham
Fire -2027
Financing
Total Cost Reserve Fund DC's �DebtFinancing Grants Other Tax Levy
Expenditures
Fire $488,500 $0 $0 $0 $0 $0 $488,500
$488,500 $01 $0 $01 $0 $0 $488,500
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Bunker Gear FD-01 $16,000 $0 $0 $0 $0 $0 $16,000 117
Fire Equipment Reserve Transfer N/A $400,000 $0 $0 $0 $0 $0 $400,000
Radio System Reseve FD-10 $30,000 $0 $0 $0 $0 $0 $30,000 130
Ice Rescue Suits FD-05 $6,000 $0 $0 $0 $0 $0 $6,000 121
Fire Hose Replacement FD-04 $14,000 $0 $0 $0 $0 $0 $14,000 120
Thermal Imaging Cameras FD-03 $15,000 $0 $0 $0 $0 $0 $15,000 119
Portable Radios FD-02 $7,500 $0 $0 $0 $0 $0 $7,500 118
$488,500 $0 $0 $0 $0 $0 $488,500
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2308 Fire Equipment Reserve $0 $400,000 $0 $400,000
2303 Fire Department Apparatus $5,000 $0 $0 $5,000
2375 Fire Radio Reserve 1 $120,000 $30,000 $0 $150,000
Municipality of Bayham
Fire -2028
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Fire $447,050 sol sol sol $0 $0 $447,050
$447,050 $0 $0 $0 1 $0 1 $0 $447,050
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Fire Equipment Reserve Transfer N/A $300,000 $0 $0 $0 $0 $0 $300,000 N/A
Pickup Truck FD-08 $65,000 $0 $0 $0 $0 $0 $65,000 124
Bunker Gear FD-01 $17,000 $0 $0 $0 $0 $0 $17,000 117
Ice Rescue Suits FD-05 $6,000 $0 $0 $0 $0 $0 $6,000
Fire Hose Replacement FD-04 $14,000 $0 $0 $0 $0 $0 $14,000 120
Radio System Reseve FD-10 $30,000 $0 $0 $0 $0 $0 $30,000 130
Thermal Imaging Cameras FD-03 $7,550 $0 $0 $0 $0 $0 $7,550 121
Portable Radios FD-02 $7,500 $0 $0 $0 $0 $0 $7,500 118
$447,050 $0 $0 $0 $0 $0 $447,050
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2308 Fire Equipment Reserve $400,000 $300,000 $0 $700,000
2303 Fire Department Apparatus $5,000 $0 $0 $5,000
2375 Fire Radio Reserve 1 $150,000 $30,0001 $0 $180,000
Municipality of Bayham
Fire -2029
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other I Tax Levy
Expenditures
Fire 1 $1,075,0001 $225,000 $0 $0 $0 $0 $850,000
$1,075,0001 $225,000 $0 $0 $0 $0 $850,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Pumper 2 FD-09 $1,000,000 $225,000 $0 $0 $0 $0 $775,000 125
Fire Equipment Reserve Transfer N/A $0 $0 $0 $0 $0 $0 $0 N/A
Bunker Gear FD-01 $17,000 $0 $0 $0 $0 $0 $17,000 117
Ice Rescue Suits FD-05 $6,000 $0 $0 $0 $0 $0 $6,000
Fire Hose Replacement FD-04 $14,000 $0 $0 $0 $0 $0 $14,000 120
Radio System Reseve FD-10 $30,000 $0 $0 $0 $0 $0 $30,000 130
Portable Radios FD-02 $8,000 $0 $0 $0 $0 $0 $8,000 118
$1,075,000 $225,000 $0 $0 $0 $0 $850,000
Budgeted Reserve Balance Opening Closing
Acc No. Acc. Name Balance Transfer to Transfer from Balance
2308 Fire Equipment Reserve $700,000 $0 $225,000 $475,000
2303 Fire Department Apparatus $5,000 $0 $0 $5,000
2375 Fire Radio Reserve $180,000 $30,000 $0 $210,000
Municipality of Bayham
Fire-2030
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Fire 1 $393,500 $0 $0 $0 $0 $0 $393,500
$393,500 $0 $0 $0 $0 $0 $393,500
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Fire Equipment Reserve Transfer N/A $350,000 $0 $0 $0 $0 $0 $350,000 N/A
Bunker Gear FD-01 $17,000 $0 $0 $0 $0 $0 $17,000 117
Ice Rescue Suits FD-05 $6,000 $0 $0 $0 $0 $0 $6,000
Fire Hose Replacement FD-04 $12,500 $0 $0 $0 $0 $0 $12,500 120
Portable Radios FD-02 1 $8,000 $0 $0 $0 $0 $0 $8,0001 118
$393,500 $0 $0 $0 $0 $0 $393,500
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2308 Fire Equipment Transfer $475,0001 $350,000 $0 $825,000
2303 Fire Department Apparatus $5,000 $0 $0 $5,000
2375 Fire Radio Reserve $210,000 $0 $0 $210,000
Municipality of Bayham
Fire -2031
Financing
Total Cost Reserve Fund �DC's �Debffinancing Grants Other Tax Levy
Expenditures
Fire $150,000 $0 $0 $0 $0 $0 $150,000
$150,0001 sol sol sol $0 $0 $150,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Fire Equipment Reserve Tr N/A $125,000 $0 $0 $0 $0 $0 $125,000 N/A
Bunker Gear FD-01 $17,000 $0 $0 $0 $0 $0 $17,000 117
Portable Radios FD-02 $8,000 $0 $0 $0 $0 $0 $8,000 118
$150,000 $0 $0 $0 $0 $0 $150,000
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2308 Fire Equipment Reserve $825,000 $125,000 $0 $950,000
2303 Fire Department Apparatus $5,000 $0 $0 $5,000
2375 Fire Radio Reserve 1 $210,0001 $30,000 $0 $240,000
Municipality of Bayham
Fire -2032
17
Financing
Total Cost Reserve Fund �DC's �Debffinancing Grants Other Tax Levy
Expenditures
Fire $11100,000 $225,000 $0 $0 $0 $0 $875,000
$1,100,0001 $225,000 $0 $0 $0 $0 $875,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Bunker Gear FD-01 $18,000 $0 $0 $0 $0 $0 $18,000 117
Tanker 2 - Replacement FD-07 $1,000,000 $225,000 $0 $0 $0 $0 $775,000 123
Exctrication Tools FD-11 $60,000 $0 $0 $0 $0 $0 $60,000 127
Fire Hose Replacement FD-04 $14,000 $0 $0 $0 $0 $0 $14,000 120
Portable Radios FD-02 1 $8,000 $0 $0 $0 $0 $0 $8,000 118
$1,100,0001 $225,000 $0 $0 $0 $0 $875,000
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2308 Fire Equipment Reserve $950,000 $0 $225,000 $725,000
2303 Fire Department Apparatus $5,000 $0 $0 $5,000
2375 Fire Radio Reserve $240,000 $30,000 $0 $270,000
1
Municipality of Bayham
Fire -2033
Financing
Total Cost Reserve Fund �DC's �Debffinancing Grants Other Tax Levy
Expenditures
Fire $40,000 $0 $0 $0 $0 $0 $40,000
$40,0001 sol sol sol $0 $0 $40,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Bunker Gear FD-01 $18,000 $0 $0 $0 $0 $0 $18,000 117
Fire Hose Replacement FD-04 $14,000 $0 $0 $0 $0 $0 $14,000 120
Portable Radios FD-02 $8,000 $0 $0 $0 $0 $0 $8,000 118
$40,000 $0 $0 $0 $0 $0 $40,000
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2308 Fire Equipment Reserve $725,000 $0 $0 $725,000
2303 Fire Department Apparatus $5,000 $0 $0 $5,000
2375 Fire Radio Reserve 1 $270,0001 $30,000 $0 $300,000
Municipality of Bayham
Fire -2034
Financing
Total Cost Reserve Fund �DC's �Debffinancing Grants Other Tax Levy
Expenditures
Fire $41,000 $0 $0 $0 $0 $0 $41,000
$41,0001 sol sol sol $0 $0 $41,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Bunker Gear FD-01 $18,000 $0 $0 $0 $0 $0 $18,000 117
Fire Hose Replacement FD-04 $14,000 $0 $0 $0 $0 $0 $14,000 120
Portable Radios FD-02 $9,000 $0 $0 $0 $0 $0 $9,000 118
$41,000 $0 $0 $0 $0 $0 $41,000
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2308 Fire Equipment Reserve $725,000 $0 $0 $725,000
2303 Fire Department Apparatus $5,000 $0 $0 $5,000
2375 Fire Radio Reserve 1 $300,0001 $30,000 $0 $330,000
Municipality of Bayham
Fire -2035
Financing
Total Cost Reserve Fund �DC's �Debffinancing Grants Other Tax Levy
Expenditures
Fire $27,000 $0 $0 $0 $0 $0 $27,000
$27,000 $0 $0 $0 $0 $0 $27,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Bunker Gear FD-01 $18,000 $0 $0 $0 $0 $0 $18,000 117
Portable Radios FD-02 $9,000 $0 $0 $0 $0 $0 $9,000 118
$27,000 $0 $0 $0 $0 $0 $27,000
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2308 Fire Equipment Reserve $725,000 $0 $0 $725,000
23031 Fire Department Apparatus 1 $5,000 $0 $0 $5,000
2375 Fire Radio Reserve 1 $330,0001 $30,000 $0 $360,000
Municipality of Bayham
Building 2026-2035
2026 1 2027 1 2028 1 2029 1 2030 1 2031 1 2032 2033 2034 2035
Expenditures
Building $0 $55,000 $0 $0 $0 $0 $0 $0 $0 $0
$0 $55,000 $0 $0 $0 $0 $0 $0 $0 $0
Financing
Tax Levy $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Reserves $0 $55,000 $0 $0 $0 $0 $0 $0 $0 $0
$0 $55,000 $0 $0 $0 $0 $0 $0 $0 $0
Municipality of Bayham
Building - 2026
Financing
Total Cost Reserve Fund I DC's Debt Financing Grants Other I Tax Levy
Expenditures
Building 1 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost I Reserve Fund I DC's Debt Financing Grants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2314 Building Reserve $63,956 $0 $0 $63,956
Municipality of Bayham
Building - 2027
Financing
Total Cost Reserve Fund DC's �DebtFinancing Grants Other Tax Levy
Expenditures
Building $55,0001 $55,000 $0 $0 $0 $0 $0
$55,0001 $55,000 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Pickup Truck B-01 $55,000 $55,000 $0 $0 $0 $0 $0 128
$55,000 $55,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2314 Building Reserve 1 $63,956 $0 $55,0001 $8,956
Municipality of Bayham
Building - 2028
Financing
Total Cost Reserve Fund I DC's IDebtFinancing Grants Other Tax Levy
Expenditures
Building $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
Financing
Capital Item No. Total Costj Reserve Fund DC's Debt Financing Grants Other ITax Levy IPage Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
23141 Building Reserve 1 $8,956 $0 $0 $8,956
Municipality of Bayham
Building -2029
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Building I $0 $0 $0 $0 $0 $0 $0
$o $01 $o $o $o $01 $o
Financing
Capital Item Capital Item No. Total Cost IReserve Fund DC's I Debt Financing Grants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2314 Building Reserve $8,956 $0 $0 $8,956
Municipality of Bayham
Building -2030
Financing
Total Cost Reserve Fund IDC's Debt Financing Grants I Other Tax Levy
Expenditures
Building $0 $0 $0 $0 $0 $0 $0
$01 0 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2314 Building Reserve $8,956 $0 $0 $8,956
Municipality of Bayham
Building -2031
Financing
Total Cost Reserve Fund DC's IlDebtFinancing Grants Other I Tax Levy
Expenditures
Building 1 $0 $0 $0 $0 $0 $0 $0
$o $o $o $01 o $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund I DC's IlDebtFinancing IGrants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2314 Building Reserve $8,956 $0 $0 $8,956
Municipality of Bayham
Building -2032
Financing
Total Cost Reserve Fund DC's IlDebtFinancing Grants Other I Tax Levy
Expenditures
Building 1 $0 $0 $0 $0 $0 $0 $0
$o $o $o $01 o $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund I DC's IlDebtFinancing IGrants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2314 Building Reserve $8,956 $0 $0 $8,956
Municipality of Bayham
Building -2033
Financing
Total Cost Reserve Fund DC's IlDebtFinancing Grants Other I Tax Levy
Expenditures
Building 1 $0 $0 $0 $0 $0 $0 $0
$o $o $o $01 o $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund I DC's IlDebtFinancing IGrants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2314 Building Reserve $8,956 $0 $0 $8,956
Municipality of Bayham
Building -2034
Financing
Total Cost Reserve Fund DC's IlDebtFinancing Grants Other I Tax Levy
Expenditures
Building 1 $0 $0 $0 $0 $0 $0 $0
$o $o $o $01 o $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund I DC's IlDebtFinancing IGrants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2314 Building Reserve $8,956 $0 $0 $8,956
Municipality of Bayham
Building -2035
Financing
Total Cost Reserve Fund DC's IlDebtFinancing Grants Other I Tax Levy
Expenditures
Building 1 $0 $0 $0 $0 $0 $0 $0
$o $o $o $01 o $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund I DC's IlDebtFinancing IGrants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2314 Building Reserve $8,956 $0 $0 $8,956
Municipality of Bayham
Public Works 2026-2035
2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
Expenditures
Roads $2,098,5001 $4,331,5001 $4,160,5001 $4,691,500 $10,069,500 $7,402,500 $13,709,500 $6,946,500 $5,164,500 $874,000
$2,098,5001 $4,331,5001 $4,160,5001 $4,691,5001 $10,069,5001 $7,402,500 $13,709,500 $6,946,500 $5,164,500 $874,000
Financing
Tax Levy $1,568,500 $2,131,500 $2,185,500 $1,546,500 $5,239,500 $2,302,500 $1,749,500 $1,096,500 $1,564,500 $199,000
Development Charges $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grants $300,000 $2,155,000 $1,925,000 $3,165,000 $4,830,000 $5,100,000 $11,930,000 $5,850,000 $3,600,000 $215,000
Other $40,000 $45,000 $50,000 $20,000 $0 $0 $30,000 $0 $0 $0
Reserves $190,000 $0 $0 $0 $0 $0 $0 $0 $0 $460,000
$2,098,5001 $4,331,5001 $4,160,5001 $4,731,5001 $10,069,5001 $7,402,5001 $13,709,500 $6,946,500 $5,164,5001 $874,000
Municipality of Bayham
Public Works-2026
Financing
1Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Exuenditures
Public Works 1 $2,098,500 $190,000 $0 $0 $300,0001 $40,000 $1,568,500
$2,098,500 $190,000 $0 $0 $300,0001 $40,0001 $1,568,500
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy ge Reference Reserve Info
Bridge/Culvert
Best Line Culvert PW-34 1 $50,000 $0 $0 $0 $0 $0 $50,0001 162
Equipment
Tandem PW-25 1 $540,000 $0 $0 $0 $0 $20,0001 $520,000 153
Tandem PW-29 1 $540,000 $0 $0 $0 $0 $20,0001 $520,0001 157
Mower PW-18 $27,0001 $0 $0 $0 $0 $0 $27,000 146
Road Construction
Murray Rd. PW-37 $72,000 $0 $0 $0 $0 $0 $72,000 165
Chute Line PW-134 $15,000 0 0 0 0 0 15,000 262
Gravel Program PW-19 $215,000 $0 $0 $0 $0 $0 $215,000 147
Carson Line PW-137 $300,000 $0 $0 $0 $300,000 $0 $0 265 OCIF
North Street PW-39 $35,000 $0 $0 $0 $0 $0 $35,000 167
Other
Sidewalks PW-07 $125,000 $25,000 $0 $0 $0 $0 $100,000 135
Road Signs PW-08 $9,000 $0 $0 $0 $0 $0 $9,000 136
Guardrails PW-09 $12,500 $0 $0 $0 $0 $0 $12,500 137
Climate Risk Assessment PW-135 $85,000 $85,000 $0 $0 $0 $0 $0 263
Pre Engineering-Port Burwell Stormwa PW-136 $35,000 $35,000 $0 $0 $0 $0 $0 264
B&C Inspection PW-20 $13,000 $0 $0 $0 $0 $0 $13,000 148
Road Side Brushing PW-01 $65,000 $15,000 $0 $0 $0 $0 $50,000 129
Hill Management PW-02 $60,000 $30,000 $0 $0 $0 $0 $30,000 130
Machine Time N/A -$100,000 $0 $0 $0 $0 $0 -$100,000
$2,098,500 $190,000 $0 $0 $300,000 $40,000 $1,568,500
Budgeted Reserve Balance
Acc No. lAcc.Name Opening Balance I Transfer to I Transfer from Closing Balance
2302 Public Works Equipment Reserve $132,000 $0 $0 $132,000
2305 Road Construction Reserve $543,732 $0 $250,0001 $293,732
2362 Federal Gas Tax Reserve $271,9211 $232,395 $0 $504,316
2363 OCIF 1 118,3011 460,8501 300,0001 $279 151
Municipality of Bayham
Public Works-2027
Financing
Total Cost Reserve Fund DC's Debt Financing I Grants Other Tax Levy
Expenditures
Public Works $4,331,500 $0 $0 $0 $2,155,0001 $45,0001 $2,131,500
$4,331,500 $0 $0 $0 $2,155,0001 $45,0001 $2,131,500
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing I Grants Other Tax Levy Page Reference Reserve Info
Bridge/Culvert
Van Order Culvert PW-41 1 $85,000 $0 $0 $0 $0 $0 $85,000 169
Best Line Culvert PW-34 $500,000 $0 $0 $0 $0 $0 $500,000 162
Equipment
Tractor&Brusher PW-42 $300,000 $0 $0 $0 $0 $20,000 $280,000 170
Pickup Truck PW-43 $60,000 $0 $0 $0 $0 $5,000 $55,000 171
Pickup Truck PW-44 $100,000 $0 $0 $0 $0 $10,000 $90,000 172
Pickup Truck PW-45 $60,000 $0 $0 $0 $0 $0 $60,000 173
Vac Unit PW-46 $105,000 $0 $0 $0 $0 $10,000 $95,000 174
Tandem PW-36 $0 $0 $0 $0 $0 $0 $0 164
Road Construction
Green Line PW-38 $250,000 $0 $0 $0 $125,000 $0 $125,000 166 Gas Tax
Baynor Rd. PW-48 $400,000 $0 $0 $0 $0 $0 $400,000 176
Bo us Rd. PW-49 $80,000 $0 $0 $0 $80,000 $0 $0 177 OCIF
Gravel Program PW-19 $215,000 $0 $0 $0 $0 $0 $215,000 147
Carson Line PW-137 $300,000 $0 $0 $0 $300,000 $0 $0 265 OCIF
James Line PW-130 $50,000 $0 $0 $0 $0 $0 $50,000 258
Other
Sidewalks PW-07 $100,000 $0 $0 $0 $0 $0 $100,000 135
Road Signs PW-08 $9,000 $0 $0 $0 $0 $0 $9,000 136
Guardrails PW-09 $12,500 $0 $0 $0 $0 $0 $12,500 137
Communication Tower PW-51 $75,000 $0 $0 $0 $0 $0 $75,000 179
PBStormSewer-PhaseIC PW-21 $1,650,000 $0 $0 $0 $1,650,000 $0 $0 149 DMAF/CWWF
Road Side Brushing PW-01 $50,000 $0 $0 $0 $0 $0 $50,000 129
Hill Management PW-02 $30,000 $0 $0 $0 $0 $0 $30,000 130
Machine Time N/A -$100,000 $01 $0 $0 $0 $0 -$100,000 N/A
$4,331,500 $0 $0 $0 $2,155,000 $45,000 $2,131,500
Budgeted Reserve Balance
Acc No. Acc.Name Opening Balance Transfer to Transfer from Closing Balance
2302 Public Works Equipment Reserve $132,000 $0 $132,000
2305 Road Construction Reserve $293,732 $0 $293,732
2362 Federal Gas Tax Reserve $504,316 $241,691 $250,000 $496,007
2363 OCIF 1 279,151 460,850 380,000 $360,001
Municipality of Bayham
Public Works-2028
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Public Works $4,160,500 $0 $0 $0 $1,925,0001 $50,0001 $2,185,500
$4,160,500 $0 $0 $0 $1,925,000 $50,000 $2,185,500
Financing
Capital Item Capital Item No. Total Cost Reserve Fund I DC's IDebtFinancing IGrants 10ther I Tax Levy I Page Reference I Reserve Info
Bridge/Culvert
$0 $0 $0 $0 $0 $0 $0
Equipment
Grader PW-35 1 $800,000 $0 $0 $0 $0 $50,000 $750,000 163
Road Construction
Arthur St. I PW-52 $18,000 $0 $0 $0 $0 $0 $18,000 180
Donnelly Drive PW-53 $18,000 $0 $0 $0 $0 $0 $18,000 181
Duke St. PW-54 $18,000 $0 $0 $0 $0 $0 $18,000 182
East St. PW-55 $35,000 $0 $0 $0 $0 $0 $35,000 183
Elgin St. PW-56 $18,000 $0 $0 $0 $0 $0 $18,000 184
Fifth St. PW-57 $35,000 $0 $0 $0 $0 $0 $35,000 185
First St. PW-58 $55,000 $0 $0 $0 $0 $0 $55,000 186
Fourth St. PW-59 $55,000 $0 $0 $0 $0 $0 $55,000 187
Garner Rd. PW-60 $15,000 $0 $0 $0 $0 $0 $15,000 188
Garnham St. PW-61 $55,000 $0 $0 $0 $0 $0 $55,000 189
Hesch St. PW-62 $18,000 $0 $0 $0 $0 $0 $18,000 190
Main St. PW-63 $110,000 $0 $0 $0 $0 $0 $110,000 191
Old Chapel St. PW-64 $35,000 $0 $0 $0 $0 $0 $35,000 192
Second St.I PW-65 $18,000 $0 $0 $0 $0 $0 $18,000 193
Sand own Rd. PW-66 $200,000 $0 $0 $0 $0 $0 $200,000 194
Short St. PW-67 $18,000 $0 $0 $0 $0 $0 $18,000 195
Third St. PW-68 $70,000 $0 $0 $0 $0 $0 $70,000 196
Wardwalk St. PW-69 $35,000 $0 $0 $0 $0 $0 $35,000 197
West St. I PW-70 $70,000 $0 $0 $0 $0 $0 $70,000 198
Gravel Pro ram PW-19 $215,000 $0 $0 $0 $0 $0 $215,000 147
Brown Rd. PW-32 $200,000 $0 $0 $0 $200,000 $0 $0 1601 Gas Tax
Tollgate Road PW-22 $85,000 $0 $0 $0 $0 $0 125,000$85,000 150
Green Line PW-38 $250,000 $0 $0 $0 $125,000 $0 $ 166 Gas Tax
Other
Sidewalks PW-07 $100,000 $0 $0 $0 $0 $0 $100,000 135
Road Signs PW-08 $9,000 $0 $0 $0 $0 $0 $9,000 136
Guardrails PW-09 $12,500 $0 $0 $0 $0 $0 $12,500 137
B&C Inspection PW-20 $13,000 $0 $0 $0 $0 $0 $13,000 148
PB Storm Sewer-Phase 1d PW-21 $1,600,000 $0 $0 $0 $1,600,000 $0 $0 149 DMAF/CWWF
Road Side Brushing PW-01 $50,000 $0 $0 $0 $0 $0 $50,000 129
Hill Management PW-02 $30,000 $0 $0 $0 $0 $0 $30,000 130
Machine Time N/A -$100,000 $0 $0 $0 $0 $0 -$100,000 N/A
$4,160,500 $0 $0 $0 $1,925,000 $50,000 $2,185,500
Budgeted Reserve Balance
Acc No. jAcc.Name Opening Balance Transfer to Transfer from Closing Balance
2302 Public Works Equipment Reserve $132,000 $0 $0 $132,000
2305 Road Construction Reserve $293,732 $0 $0 $293,732
2362 Federal Gas Tax Reserve $496,007 $241,691 $200,000 $537,697
2363 OCIF 1 360,001 0 0 $360 001
Municipality of Bayham
Public Works-2029
Financing
Total Cost Reserve Fund I DC's Debt Financing Grants Other Tax Levy
Expenditures
Public Works 1 $4,691,500 $0 $0 $0 $3,165,0001 $20,0001 $1,546,500
$4,691,500 $0 $0 $0 $3,165,0001 $20,0001 $1,546,500
Financing
Capital Item Capital Item No. ITotal Cost I Reserve Fund DC's IDebtFinancing IGrants 10ther I Tax Levy I Page Reference I Reserve Info
Bridge/Culvert
$0 $0 $0 $0 $0 $0 $0
Equipment
Tandem PW-72 $530,000 $0 $0 $0 $0 $20,0001 $550,0001 200
Road Construction
Brown Rd. PW-73 $75,000 $0 $0 $0 $75,000 $0 $0 201 Gas Tax
Coyle Rd. PW-74 $100,000 $0 $0 $0 $100,000 $0 $0 202 Gas Tax
Eden Line PW-75 $250,000 $0 $0 $0 $0 $0 $250,000 203
Ba ham Drive PW-76 $350,000 $0 $0 $0 $0 $0 $350,000 204
Travis St. PW-77 $20,000 $0 $0 $0 $0 $0 $20,000 205
Gray St. I PW-78 1 $30,000 $0 $0 $01 0 $0 $30,0001 206
Gravel Program PW-19 1 $215,000 $0 $0 $0 $0 $0 $215,0001 147
Other
Sidewalks PW-07 $100,000 $0 $0 $0 $0 $0 $100,000 135
Road Signs PW-08 $9,000 $0 $0 $0 $0 $0 $9,000 136
Guardrails PW-09 $12,500 $0 $0 $0 $0 $0 $12,500 137
PB Storm Sewer-Phase 1E-F PW-40 $2,990,000 $0 $0 $0 $2,990,000 $0 $0 168 DMAF/CWWF
Road Side Brushing PW-01 $50,000 $0 $0 $0 $0 $0 $50,000 129
Roads Need Stud PW-107 $30,000 $0 $0 $0 $0 $0 $30,000 235
Hill Management PW-02 $30,000 $0 $0 $0 $0 $0 $30,000 130
Machine Time N/A -$100,000 $0 $0 $0 $0 $0 -$100,000 N/A
$4,691,500 $0 $0 $0 $3,165,000 $20,000 $1,546,500
Budgeted Reserve Balance
Acc No. Acc.Name Opening Balance Transfer to Transfer from Closing Balance
2302 Public Works Equipment Reserve $132,000 $0 $0 $132,000
2305 Road Construction Reserve $293,732 $0 $0 $293,732
2362 Federal Gas Tax Reserve $537,697 $220,000 $175,000 $582,697
2363 OCIF 1 1 360,001 01 0 $360,001
Municipality of Bayham
Public Works-2030
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Public Works $10,069,500 $0 $0 $0 $4,830,0001 $0 $5,239,500
$10,069,500 $0 $0 $0 $4,830,0001 $0 $5,239,500
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's I Debt Financing Grants I Other I Tax Levy I Page Reference I Reserve Info
Bridge/Culvert
$0 $0 $0 $0 $0 $0 $0
Equipment
Pick Up Trucks PW-26 1 $195,000 $0 $0 $0 $0 $0 $195,0001 154
Road Construction
Green Line PW-80 $100,000 $0 $0 $0 $100,000 $0 $0 208 Gas Tax
Elliott Rd. PW-81 $50,000 $0 $0 $0 $50,000 $0 $0 209 Gas Tax
Li"
i ht Line PW-82 $3,000,000 $0 $0 $0 $0 $0 $3,000,000 210
Jackson Line East PW-83 $500,000 $0 $0 $0 $0 $0 $500,000 211
Ann St. I PW-84 $80,000 $0 $0 $0 $0 $0 $80,000 212
Centre St. PW-85 $160,000 $0 $0 $0 $0 $0 $160,000 213
Chestnut St. PW-86 $50,000 $0 $0 $0 $0 $0 $50,000 214
Edison Drive PW-87 $190,000 $0 $0 $0 $0 $0 $190,0001 215
Elm St. PW-88 $150,000 $0 $0 $0 $0 $0 $150,0001 216
Front St. PW-89 $15,000 $0 $0 $0 $0 $0 $15,000 217
Fulton St. PW-90 $45,000 $0 $0 $0 $0 $0 $45,000 218
King St. PW-91 $30,000 $0 $0 $0 $0 $0 $30,000 219
North St. PW-92 $65,000 $0 $0 $0 $0 $0 $65,000 220
Oak St. PW-93 $15,000 $0 $0 $0 $0 $0 $15,000 221
Old Mill Line PW-94 $50,000 $0 $0 $0 $0 $0 $50,000 222
Otter St. PW-95 $15,000 $0 $0 $0 $0 $0 $15,000 223
Pearl St. PW-96 $30,000 $0 $0 $0 $0 $0 $30,000 224
Pine St. PW-97 $25,000 $0 $0 $0 $0 $0 $25,0001 225
Queen St. PW-98 $15,000 $0 $0 $0 $0 $0 $15,0001 226
Snow St. PW-99 $30,000 $0 $0 $0 $0 $0 $30,000 227
Soper Rd. PW-100 $75,000 $0 $0 $0 $0 $0 $75,000 228
Union St.I PW-101 $80,000 $0 $0 $0 $0 $0 $80,000 229
Walnut St. PW-102 $35,000 $0 $0 $0 $0 $0 $35,000 230
Water St. PW-103 $15,000 $0 $0 $0 $0 $0 $15,000 231
Gravel Program PW-19 $215,000 $0 $0 $0 $0 $0 $215,000 147
Other
Sidewalks PW-07 $100,000 $0 $0 $0 $0 $0 $100,000 135
Road Signs PW-08 $9,000 $0 $0 $0 $0 $0 $9,000 136
Guardrails PW-09 $12,500 $0 $0 $0 $0 $0 $12,500 137
B&C Inspection PW-20 $13,000 $0 $0 $0 $0 $0 $13,000 148
Road Side Brushing PW-01 $50,000 $0 $0 $0 $0 $0 $50,000 129
Hill Management PW-02 $30,000 $0 $0 $0 $0 $0 $30,000 130
PB Storm Sewer-Phase 2 PW-50 $4,680,000 $0 $0 $0 $4,680,000 $0 $0 178 DMAF/CWWF
Lakeshore Line Stud PW-33 $45,000 $0 $0 $0 $0 $0 $45,000 161
Machine Time N/A -$100,000 $0 $0 $0 $0 $0 -$100,000 N/A
$10,069,500 $0 $0 $0 $4,830,000 $0 $5,239,500
Budgeted Reserve Balance
Acc No. Acc.Name Opening Balance Transferto Transfer from Closing Balance
2302 Public Works Equipment Reserve $132,000 $0 $0 $132,000
2305 Road Construction Reserve $293,732 $0 $0 $293,732
2362 Federal Gas Tax Reserve $582,697 $220,000 $150,000 $652,697
2363 OCIF 360,0011 0 0 $360,0011
Municipality of Bayham
Public Works-2031
Financing
Total Cost Reserve Fund DC's Debt Financing Grants I Other I Tax Levy
Expenditures
Public Works $7,402,500 $0 $0 $0 $5,100,0001 $0 $2,302,500
$7,402,500 $0 $0 $0 $5,100,0001 $0 $2,302,500
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing lGrants 10ther I Tax Levy Page Reference Reserve Info
Bridge/Culvert
$0 $0 $0 $0 $0 $0 $0
Equipment
$0 $0 $0 $0 $0 $0 $0
Road Construction
Addison St PW-109 $96,000 $0 $0 $0 $0 $0 $96,000 237
Burwell St PW-110 $16,000 $0 $0 $0 $0 $0 $16,000 238
Cowper St PW-111 $32,000 $0 $0 $0 $0 $0 $32,000 239
Elizabeth St PW-112 $112,000 $0 $0 $0 $0 $0 $112,000 240
Erieus St PW-113 $96,000 $0 $0 $0 $0 $0 $96,000 241
Hannah St PW-114 $16,000 $0 $0 $0 $0 $0 $16,000 242
Hurley St PW-115 $32,000 $0 $0 $0 $0 $0 $32,000 243
Milton St PW-116 $48,000 $0 $0 $0 $0 $0 $48,000 244
Newton St PW-117 $48,000 $0 $0 $0 $0 $0 $48,000 245
Pitt St PW-118 $112,000 $0 $0 $0 $0 $0 $112,000 246
Robinson St PW-119 $64,000 $0 $0 $0 $0 $0 $64,000 247
Shakespeare St PW-120 $80,000 $0 $0 $0 $0 $0 $80,000 248
Southey St PW-121 $16,000 $0 $0 $0 $0 $0 $16,000 249
Strachan St PW-122 $64,000 $0 $0 $0 $0 $0 $64,000 250
Submariners Way PW-123 $16,000 $0 $0 $0 $0 $0 $16,000 251
Tennyson St PW-124 $16,000 $0 $0 $0 $0 $0 $16,000 252
Victoria St PW-125 $32,000 $0 $0 $0 $0 $0 $32,000 253
Waterloo St PW-126 $80,000 $0 $0 $0 $0 $0 $80,000 254
Wellington St PW-106 $64,000 $0 $0 $0 $0 $0 $64,000 234
William St PW-105 $16,000 $0 $0 $0 $0 $0 $16,000 233
Ridge Line PW-15 $250,000 $0 $0 $0 $0 $0 $250,000 143
Mitchell Road PW-13 $180,000 $0 $0 $0 $0 $0 $180,000 141
Somers Road PW-12 $250,000 $0 $0 $0 $0 $0 $250,000 140
Carson Road PW-47 $160,000 $0 $0 $0 $160,000 $0 $0 175 OCIF
Toll Gate&Black Bridge Line PW-11 $250,000 $0 $0 $0 $0 $0 $250,000 139
Gravel Program PW-19 $215,006 $0 $0 $0 $0 $0 $215,000 147
Other
Sidewalks PW-07 $100,000 $0 $0 $0 $0 $0 $100,000 135
Road Signs PW-08 $9,000 $0 $0 $0 $0 $0 $9 000 136
Guardrails PW-09 $12,500 $0 $0 $0 $0 $0 $12,500 137
PS Storm Sewer-Phase 3 PW-71 $4,940,000 $0 $0 $0 $4 940,000 $0 $0 199 DMAF/CWWF
Road Side Brushing PW-01 $50,000 $0 $0 $0 $0 $0 $50,000 129
Hill Management PW-02 $30,000 $30,000 130
Machine Time N/A -$100,000 $0 $0 $0 $0 $0 -$100,000 N/A
$7,402,500 $0 $0 $0 $5,100,000 $0 $2,302,500
Budgeted Reserve Balance Opening
Acc No. jAcc.Name Balance Transfer to Transfer from Closing Balance
2302 Public Works Equipment Reserve $132,000 $0 $0 $132,000
2305 Road Construction Reserve $293,732 $0 $0 $293,732
2362 Federal Gas Tax Reserve $652,697 $230,000 $0 $882,697
2363 OCIF 1 360,001 01 160,0001 $200 001
Municipality of Bayham
Public Works-2032
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other I Tax Levy
Expenditures
Public Works 1 $13,709,500 $0 $0 $0 $11,930,0001 $30,0001 $1,749,500
$13,709,500 $0 $0 $0 $11,930,0001 $30,0001 $1,749,500
Financing
Capital Item Capital Item No. ITotal Cost I Reserve Fund I DC's IDebtFinancing JGrants 10ther I Tax Levy IPageReference Reserve Info
Bridge/Culvert
$0 $0 $0 $0 $0 $0 $0
Equipment
Backhoe PW-14 1 $240,000 $0 $0 $0 $0 $30,0001 $210,0001 142
Road Construction
Chute Line 1 PW-05 $230,000 $0 $0 $0 $230,000 $0 $0 133 Gas Tax
Jackson Line West PW-03 $575,000 $0 $0 $0 $0 $0 $575,000 131
Tunnel Line PW-04 $325,000 $0 $0 $0 $0 $0 $325,000 132
Ottergate Line PW-06 $190,000 $0 $0 $0 $0 $0 $190,000 134
Shady Lane PW-10 $120,000 $0 $0 $0 $0 $0 $120,000 138
Gravel Program PW-19 $215,000 $0 $0 $0 $0 $0 $215,000 147
Other
Road Signs PW-08 $9,000 $0 $0 $0 $0 $0 $9,000 136
Guardrails PW-09 $12,500 $0 $0 $0 $0 $0 $12,500 137
Road Side Brushing PW-01 $50,000 $0 $0 $0 $0 $0 $50,000 129
Hill Management PW-02 $30,000 $30,000 130
Sidewalks PW-07 $100,000 $0 $0 $0 $0 $0 $100,000 135
Machine Time N/A -$100,000 $0 $0 $0 $0 $0 -$100,000 N/A
PB Storm Sewer-Phase 4 PW-79 1 $11,700,000 $0 $0 $0 $11,700,000 $0 $0 207 DMAF/CWWF
B&C Inspection PW-20 $13,000 $0 $0 $0 $0 $0 $13,000 148
$0 $0 $0 $0 $0 $0
$13,709,500 $0 $0 $0 $11,930,000 $30,000 $1,749,500
Budgeted Reserve Balance Opening
Acc No. Acc.Name Balance Transfer to Transfer from Closing Balance
2302 Public Works Equipment Reserve $132,000 $0 $0 $132,000
2305 Road Construction Reserve $293,732 $0 $0 $293,732
2362 Federal Gas Tax Reserve $882,697 $230,000 $230,000 $882,697
2363 OCIF 1 200,001 0 0 $200,001
Municipality of Bayham
Public Works-2033
Financing
Total Cost Reserve Fund I DC's Debt Financing Grants Other Tax Levy
Expenditures
Public Works 1 $6,946,500 $0 $0 $0 $5,850,0001 $0 $1,096,500
$6,946,500 $0 $0 $0 $558509000 $0 $15096,500
Financing
Ca ital Item Capital Item No. ITotal Cost IReserveFund DC's Debt Financing lGrants 10ther I Tax Levy IPageReference Reserve Info
Bridge/Culvert
$0 $0 $0 $0 $0 $0 $0
Equipment
$0 $0 $0 $0 $0 $0 $0
Road Construction
Tunnel Line PW-23 $200,000 $0 $0 $0 $0 $0 $200,000 151
Maple Grove PW-30 $200,000 $0 $0 $0 $0 $0 $200,000 158
Springer Hill PW-31 $170,000 $0 $0 $0 $0 $0 $170,000 159
Eden Line West PW-127 $100,000 $0 $0 $0 $0 $0 $100,000 255
Mitchell PW-128 $110,000 $0 $0 $0 $0 $0 $110,000 256
Gravel Program PW-19 $215,000 $0 $0 $0 $0 $0 $215,000 147
$0 $0 $0 $0 $0 $0 $0
Other
Road Signs PW-08 $9,000 $0 $0 $0 $0 $0 $9,000 136
Guardrails PW-09 $12,500 $0 $0 $0 $0 $0 $12,500 137
Road Side Brushing PW-01 $50,000 $0 $0 $0 $0 $0 $50,000 129
PB Storm Sewer-Phase 5 PW-104 $5,850,000 $0 $0 $0 $5,850,000 $0 $0 232 DMAF/CWWF
Hill Management PW-02 $30,000 $30,000 130
Machine Time N/A -$100,000 $0 $0 $0 $0 $0 -$100,000 N/A
Sidewalks PW-07 $100,000 $0 $0 $0 $0 $0 $100,000 135
$65946,500 $0 $0 $0 $55850,000 $0 $15096,500
Budgeted Reserve Balance Opening
Acc No. Acc.Name Balance Transfer to Transfer from Closing Balance
2302 Public Works Equipment Reserve $132,000 $0 $0 $132,000
2305 Road Construction Reserve $293,732 $0 $0 $293,732
2362 Federal Gas Tax Reserve $882,697 $230,000 $0 $1,112,697
2363 OCIF $200,001 0 0 $200,001
Municipality of Bayham
Public Works-2034
Financing
Total Cost Reserve Fund I DC's Debt Financing Grants Other Tax Levy
Expenditures
Public Works 1 $5,164,500 $0 $0 $0 $3,600,0001 $0 $1,564,500
$5,164,500 $0 $0 $0 $356009000 $0 $15564,500
Financing
Ca ital Item Capital Item No. ITotal Cost IReserveFund DC's I Debt Financing lGrants 10ther I Tax Levy jPageReference Reserve Info
Bridge/Culvert
$0 $0 $0 $0 $0 $0 $0
Equipment
Pick Up PW-24 1 $70,000 $0 $0 $0 $0 $0 $70,0001 152
Road Construction
Works I PW-129 $60,000 $0 $0 $0 $0 $0 $60,000 257
Sand own Road Resurface PW-132 $300,000 $0 $0 $0 $0 $0 $300,000 260
Chapel Street PW-133 $30,000 $0 $0 $0 $0 $0 $30,000 261
Tollgate Road PW-16 $325,000 $0 $0 $0 $0 $0 $325,000 144
Vienna Line PW-27 $220,000 $0 $0 $0 $0 $0 $220,000 155
Gravel Program PW-19 $215,000 $0 $0 $0 $0 $0 $215,000 147
Other
Road Signs PW-08 $9,000 $0 $0 $0 $0 $0 $9,000 136
SW Fac Man PW-17 $75,000 $0 $0 $0 $0 $0 $75,000 145
Guardrails PW-09 $12,500 $0 $0 $0 $0 $0 $12,500 137
Road Side Brushing PW-01 $50,000 $0 $0 $0 $0 $0 $50,000 129
Hill Management PW-02 $30,000 $0 $0 $0 $0 $0 $30,000 130
B&C Inspection PW-20 $13,000 $0 $0 $0 $0 $0 $13,000 148
PB Storm Sewer-Phase 6 PW-28 $3,600,000 $0 $0 $0 $3,600,000 $0 $0 156 DMAF/CWWF
BC OSIM PW-131 $15,000 $0 $0 $0 $0 $0 $15,000 257
Roads Need Stud PW-107 $40,000 $0 $0 $0 $0 $0 $40,000 235
Sidewalks PW-07 $100,000 $0 $0 $0 $0 $0 $100,000 135
$5,164,500 $0 $0 $0 $3,600,000 $0 $1,564,500
Budgeted Reserve Balance Opening
Acc No. Acc.Name Balance Transfer to Transfer from Closing Balance
2302 Public Works Equipment Reserve $132,000 $0 $0 $132,000
2305 Road Construction Reserve $293,732 $0 $0 $293,732
2362 Federal Gas Tax Reserve $1,112,697 $230,000 $0 $1,342,697
2363 OCIF 1 1 $200,001 01 0 $200,001
Municipality of Bayham
Public Works-2035
Financing
Total Cost Reserve Fund I DC's Debt Financing Grants I Other I Tax Levy
Expenditures
Public Works 1 $874,0001 $460,000 $0 $0 $215,000 $0 $199,000
$874,0001 $460,000 $0 $0 $2159000 $0 $1999000
Financing
Capital Item Capital Item No. ITotal Cost IReserveFund DC's Debt Financing IGrants 10ther I Tax Levy IPageReference Reserve Info
Bridge/Culvert
Tunnel Line Culvert removal PW-108 $460,0001 $460,000 $0 $0 $0 $0 $01 236
Equipment
$0 $0 $0 $0 $0 $0 $0
Road Construction
Gravel Program PW-19 $215,000 $0 $0 $0 $215,000 $0 $0 147 OCIF
$0 $0 $0 $0 $0 $0 $0
Other
Sidewalks PW-07 $100,000 $0 $0 $0 $0 $0 $100,000 135
Road Signs PW-08 $9,000 $0 $0 $0 $0 $0 $9,000 136
Guardrails PW-09 $10,000 $0 $0 $0 $0 $0 $10,000 137
Road Side Brushing PW-01 $50,000 $0 $0 $0 $0 $0 $50,000 129
Hill Management PW-02 $30,000 $0 $0 $0 $0 $0 $30,000 130
$0 $0 $0 $0 $0 $0 $0
$874,0001i $460,000 $0 $0 $215,000 $0 $199,000
Budgeted Reserve Balance Opening
Acc No. Acc.Name Balance Transfer to Transfer from Closing Balance
2302 Public Works Equipment Reserve $132,000 $0 $0 $132,000
2305 Road Construction Reserve $293,732 $0 $460,000 -$166,268
2362 Federal Gas Tax Reserve $1,342,697 $230,000 $0 $1,572,697
2363 OCIF 1 1 $200,001 0 0 $200,001
Municipality of Bayham
Water 2026-2035
2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
Expenditures
Water $0 $80,5001 $18,197,0001 $309,0001 $388,0001 $437,000 $32,000 $33,000 $72,500 $0
$0 $80,5001 $18,197,0001 $309,0001 $388,0001 $437,0001 $32,000 $33,000 $72,500 $0
Financing
Tax Levy $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $16,883,000 $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Reserves $0 $80,5001 $1,31410001 $309,0001 $388,0001 $437,0001 $32,000 $33,000 $72,500 $0
$0 $80,5001 $18,197,0001 $309,0001 $388,0001 $437,0001 $32,000 $33,0001 $72,500 $0
Municipality of Bayham
Water-2026
Financing
Total Cost Reserve Fund I DC's Debt Financing Grants Other I Tax Levy
Expenditures
Water $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance
Acc No. lAcc. Name Opening Balance Transfer to Transfer from I Closing Balance
2310 1 Water Reserve $928,9811 $250,000 $0 $1,178,981
Municipality of Bayham
Water-2027
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Water $80,500 $80,500 $01 $01 $0 $0 $0
$80,500 $80,500 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Pickup Truck W-02 $33,000 $33,000 $0 $0 $0 $0 $0 267
Vac Unit PW-46 $47,500 $47,500 $0 $0 $0 $0 $0 174
$80,500 $80,500 $0 $0 $0 $0 $0
Budgeted Reserve Balance
Acc No. jAcc. Name Opening Balance Transfer to Transfer from Closing Balance
2310 Water Reserve $1,178,9811 $250,000 $80,5001 $1,348,481
Municipality of Bayham
Water-2028
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other I Tax Levy
Expenditures
Water $18,197,000 $1,314,000 $0 $0 $16,883,000 $0 $0
$18,197,0001 $1,314,000 $0 $0 $16,883,000 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Bayham water system W-08 $76,000 $76,000 $0 $0 $0 $0 $0 273
Bayham Water Lines W-09 $1,238,000 $1,238,000 $0 $0 $0 $0 $0 274
PBSS Capital W-10 $16,883,000 $0 $0 $0 $16,883,000 $0 $0 275
$18,197,000 $1,314,000 $0 $0 $16,883,000 $0 $0
Budgeted Reserve Balance
Acc No. Acc. Name Opening Balance Transfer to Transfer from Closing Balance
2310 Water Reserve $1,348,481 $250,0001 $1,314,0001 $284,481
Municipality of Bayham
Water-2029
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Water $309,000 $309,000 $0 $0 $0 $0 $0
$309,000 $309,000 $0 $01 $0 $01 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Water Financial Plan W-03 $20,000 $20,000 $0 $0 $0 $0 $0 268
Richmond Well Review W-04 $25,000 $25,000 $0 $0 $0 $0 $0 269
Watermain Re-insulati W-06 $58,000 $58,000 $0 $0 $0 $0 $0 271
Bayham water system W-08 $78,000 $78,000 $0 $0 $0 $0 $0 273
Booster Upgrades W-05 $65,000 $65,000 $0 $0 $0 $0 $0 270
SCADA Computer W-01 $28,000 $28,000 $0 $0 $0 $0 $0 266
Pickup Truck W-02 $35,000 $35,000 $0 $0 $0 $0 $0 267
$309,000 $309,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance
Acc No. jAcc. Name Opening Balance Transfer to Transfer from Closing Balance
2310 1 Water Reserve 1 $284,4811 $250,0001 $309,0001 $225,481
Municipality of Bayham
Water-2030
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other I Tax Levy
Expenditures
Water $388,000 $388,000 $0 $0 $0 $0 $0
$388,0001 $388,000 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy I Page Reference
Water Meter Replacement W-07 $388,000 $388,000 $0 $0 $0 $0 $01 272
$388,000 $388,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance
Acc No. jAcc. Name Opening Balance Transfer to Transfer from Closing Balance
2310 1 Water Reserve 1 $225,481 $250,0001 $388,000 $87,481
Municipality of Bayham
Water-2031
117
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Water $437,0001 $437,000 $0 $0 $0 $0 $01
$437,0001 $437,000 $0 $0 $0 $0 2
Financing
rWa�ter
apital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
ter replacements W-07 $400,000 $400,000 $0 $0 $0 $0 $0 272
Pickup Truck W-02 $37,000 $37,000 $0 $0 $0 $0 $0 267
$437,000 $437,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
$2,310 1 Water Reserve $87,481 $250,000 $437,000 -$99,519
Municipality of Bayham
Water-2032
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Water $32,0001 $32,000 $0 $0 $0 $0 $0
$32,0001 $32,000 $0 $0 $0 $0 1 $0
Financing
Capital Item I Capital Item No. ITotal Cost lReserve Fund DC's IDebt Financing lGrants 10ther Tax Levy Page Reference
Water chamber rehab W-11 I $32,000 $32,000 $0 $01 $0 $0 $0 276
$32,000 $32,000 $0 $01 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
$2,310 1 Water Reserve -$99,519 $225,000 $32,000 $93,481
Municipality of Bayham
Water-2033
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Water $33,0001 $33,000 $0 $0 $0 $0 $0
$33,0001 $33,000 $0 $0 $0 $0 1 $0
Financing
Capital Item I Capital Item No. ITotal Cost lReserve Fund DC's I Debt Financing Grants Other Tax Levy Page Reference
Water chamber rehab W-11 I $33,00,01 $33,000 $0 $0 $0 $0 $0 276
$33,0001 $33,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
$2,310 lWater Reserve $93,481 $225,0001 $33,0001 $285,481
Municipality of Bayham
Water-2034
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Water $72,5001 $72,500 $0 $0 $0 $0 $0
$72,5001 $72,500 $0 $0 $0 $0 1 $0
Financing
Capital Item I Capital Item No. ITotal Cost lReserve Fund DC's IDebt Financing lGrants 10ther Tax Levy I Page Reference
Water chamber rehab W-11 1 $25,000 $25,000 $0 $0 $0 $0 $0 276
Richmond Well Review W-04 $25,000 $25,000 $0 $0 $0 $0 $0 269
Water Financial Plan W-03 $22,500 $22,500 $0 $0 $0 $0 $0 268
$72,500 $72,500 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
$2,310 lWater Reserve $285,481 $225,0001 $72,5001 $437,981
Municipality of Bayham
Water-2035
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Water $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 1 $0
Financing
Capital Item I Capital Item No. ITotal Cost lReserve Fund DC's IDebt Financing lGrants 10ther Tax Levy I Page Reference
1 $0 $o $0 $o $o $o $0
$0 $o $o $o $o $o $0
$0 $o $o $o $o $o $0
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
$2,310 1 Water Reserve $437,981 $225,000 $0 $662,981
Municipality of Bayham
Wastewater 2026-2035
2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
Expenditures
Wastewater $656,0001 $878,5001 $176,0001 $17,605,0001 $18,075,000 $203,000 $112,000 $217,000 $162,500 $0
$656,0001 $878,5001 $176,0001 $17,605,0001 $18,075,000 $203,000 $112,000 $217,000 $162,500 $0
Financing
Tax Levy $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $17,389,000 $17,911,000 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Reserves $656,0001 $878,5001 $176,0001 $216,0001 $164,0001 $203,000 $112,000 $217,0001 $162,500 $0
$65670001 $878,5001 $176,0001 $17,605,0001 $18,075,0001 $203,0001 $112,000 $217,0001 $162,500 $0
Municipality of Bayham
Wastewater-2026
Financing
Total Cost Reserve Fund DC's �DebtFinancing Grants Other Tax Levy
Expenditures
Wastewater 1 $656,0001 $656,000 $0 $0 $0 $0 $0
$656,0001 $656,000 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. ITotal Cost I Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Manhole rehab WW-08 $27,000 $27,000 $0 $0 $0 $0 $0 284
System Equipment WW-03 $21,000 $21,000 $0 $0 $0 $0 $0 279
Air Blowsers WW-05 $28,000 $28,000 $0 $0 $0 $0 $0 281
Alarm Communic. WW-04 $50,000 $50,000 $0 $0 $0 $0 $01 280
Wastewater treatment plant land WW-13 1 $530,0001 $530,000 $0 $0 $0 $0 $01 289
$656,0001 $656,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2312 1 Wastewater Reserve 1 $3,610,2391 $250,0001 $656,0001 $3,204,239
Municipality of Bayham
Wastewater -2027
Financing
Total Cost Reserve Fund DC's �Debffinancina Grants Other Tax Levy
Expenditures
Wastewater $878,500 $878,500 $0 $0 $0 $0 $0
$878,500 $878,500 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Pickup truck W-02 $33,000 $33,000 $0 $0 $0 $0 $0 267
Vac Unit PW-46 $47,500 $47,500 $0 $0 $0 $0 $0 174
Communication tow PW-51 $75,000 $75,000 $0 $0 $0 $0 $0 179
Manhole rehab WW-08 $27,000 $27,000 $0 $0 $0 $0 $0 284
Pumps St 7 and 8 WW-12 $150,000 $150,000 $0 $0 $0 $0 $0 288
WWTP EA WW-14 $164,000 $164,000 $0 $0 $0 $0 $0 290
WWTP Eng WW-11 $382,000 $382,000 $0 $0 $0 $0 $0 287
$878,500 $878,500 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from I Closing Balance
2312 Wastewater Reserve 1 $3,204,2391 $250,0001 $878,5001 $2,575,739
Municipality of Bayham
Wastewater-2028
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Wastewater $176,0001 $176,000 $0 $0 $0 $0 $0
I $176,0001 $176,000 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
System Equipment WW-01 $51,000 $51,000 $0 $0 $0 $0 $0 277
SCADA WW-02 $30,000 $30,000 $0 $0 $0 $0 $0 278
Parking Lot WW-09 $67,000 $67,000 $0 $0 $0 $0 $0 285
Manhole rehab 1 WW-08 $28,0001 $28,000 $0 $01 $0 $0 $0 284
$176,0001 $176,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. Acc. Name Balance Transfer to Transfer from Balance
2312 Wastewater Reserve $2,575,739 $250,000 $176,000 $2,649,739
Municipality of Bayham
Wastewater-2029
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Wastewater $17,605,000 $216,000 $0 $0 $17,389,0001 $0 $0
$17,605,0001 $216,000 $0 $0 $17,389,000 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
System Equipment WW-01 $52,000 $52,000 $0 $0 $0 $0 $0 277
Manhole rehab WW-08 $29,000 $29,000 $0 $0 $0 $0 $0 284
Water Financial Pla W-03 $20,000 $20,000 $0 $0 $0 $0 $0 268
Pickup Truck W-02 $35,000 $35,000 $0 $0 $0 $0 $0 267
SCADA Packs WW-06 $80,000 $80,000 $0 $0 $0 $0 $0 282
WWTP WW-10 $17,389,000 $0 $0 $0 $17,389,000 $0 $0 286
$17,605,0001 $216,000 $0 $0 $17,389,000 $0 $0
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2312 1 Wastewater Reserve $2,649,7391 $250,000 $216,0001 $2,683,739
Municipality of Bayham
Wastewater-2030
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Wastewater $18,075,0001 $164,000 $0 $0 $17,911,0001 $01 $0
$18,075,0001 $164,000 $0 $0 $17,911,000 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
System Equipment WW-01 $54,000 $54,000 $0 $0 $0 $0 $0 277
Manhole rehab WW-08 $30,000 $30,000 $0 $0 $0 $0 $0 284
SCADA Packs WW-06 $80,000 $80,000 $0 $0 $0 $0 $0 282
WWTP WW-10 $17,911,000 $0 $0 $0 $17,911,000 $0 $0 286
$18,075,000 $164,000 $0 $0 $17,911,000 $0 $0
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance I Transfer to I Transfer from Closing Balance
2312 Wastewater Reserve 1 $2,683,7391 $250,0001 $164,000 $2,769,739
Municipality of Bayham
Wastewater-2031
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Wastewater I $203,000 $203,000 $0 $0 $01 $01 $0
$203,000 $203,000 $0 $0 $0 $0 $0
Financing
Capital Item 1 Capital Item No. Total Cost Reserve Fund I DC's I Debt Financing Grants Other ITax Levy jPage Reference
System Equipment WW-01 $55,000 $55,000 $0 $0 $0 $0 $01 277
Pickup Truck W-02 $37,000 $37,000 $0 $0 $0 $0 $0 268
SCADA Packs WW-06 $80,000 $80,000 $0 $0 $0 $0 $0 282
Manhole rehab WW-08 $31,000 $31,000 $0 $0 $0 $0 $0 284
$203,000 $203,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name I Balance Transfer to Transfer from Balance
2312 Wastewater Reserve 1 $2,769,739 $250,0001 $203,0001 $2,816,739
Municipality of Bayham
Wastewater-2032
Financing
Total Cost Reserve Fund FDcs Debt Financing Grants Other Tax Levy
Expenditures
Wastewater $112,0001 $112,000 $0 $0 $0 $0 $0
$112,0001 $112,000 $0 $0 $0 $01 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Manhole rehab WW-08 $32,000 $32,000 $0 $0 $0 $0 $0 284
SCADA Packs WW-06 $80,000 $80,000 $0 $0 $0 $0 $0 282
$112,000 $112,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
2312 Wastewater Reserve 1 $2,816,7391 $250,0001 $112,0001 $2,954,739
Municipality of Bayham
Wastewater-2033
Financing
Total Cost Reserve Fund FDcs Debt Financing Grants Other Tax Levy
Expenditures
Wastewater $217,0001 $217,000 $0 $0 $0 $0 $0
$217,0001 $217,000 $0 $0 $0 $01 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Manhole rehab WW-08 $33,000 $33,000 $0 $0 $0 $0 $0 284
SCADA Packs WW-06 $80,000 $80,000 $0 $0 $0 $0 $0 282
Forcemain Chamber WW-07 $104,000 $104,000 $0 $0 $0 $0 $0 283
$217,000 $217,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
2312 Wastewater Reserve $2,954,7391 $250,0001 $217,0001 $2,987,739
Municipality of Bayham
Wastewater-2034
Financing
Total Cost Reserve Fund FDcs Debt Financing Grants Other Tax Levy
Expenditures
Wastewater $162,5001 $162,500 $0 $0 $0 $0 $0
$162,5001 $162,500 $0 $0 $0 $01 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Forcemain Chamber WW-07 $107,000 $107,000 $0 $0 $0 $0 $0 283
Manhole rehab WW-08 $33,000 $33,000 $0 $0 $0 $0 $0 284
Water Financial Plan W-03 $22,500 $22,500 $0 $0 $0 $0 $0 268
$162,500 $162,500 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
2312 Wastewater Reserve 1 $2,987,7391 $250,0001 $162,5001 $3,075,239
Municipality of Bayham
Wastewater-2035
Financing
Total Cost Reserve Fund FDcs Debt Financing Grants Other Tax Levy
Expenditures
Wastewater $0 $0 $0 $0 $0 $0 $0
$o $0 1 $o $o $o $0 1 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
$0 $01 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. Acc. Name Balance Transfer to Transfer from Balance
2312 Wastewater Reserve $3,075,239 $250,0001 $0 $3,325,239
Municipality of Bayham
Parks & Recreation 2026-2035
2026 1 2027 2028 2029 2030 1 2031 1 2032 2033 2034 2035
Expenditures
Parks & Recreation $475,0001 $720,0001 $380,0001 $110,0001 $90,0001 $90,000 $90,000 $90,000 $90,000 $50,000
$475,0001 $720,0001 $380,0001 $110,0001 $90,0001 $50,000 $90,000 $90,000 $90,000 $50,000
Financing
Tax Levy $65,000 $495,000 $80,000 $20,000 $0 $0 $0 $0 $0 $50,000
Development Charges $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grants $0 $225,000 $300,000 $90,000 $90,000 $90,000 $90,000 $90,000 $90,000 $0
Other $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Reserves 1 $410,0001 $0 $0 $0 $0 $0 $0 $0 $0 $0
$475,0001 $720,0001 $380,0001 $110,0001 $90,0001 $90,0001 $90,000 $90,000 $90,0001 $50,000
Municipality of Bayham
Parks & Recreation -2026
Financing
Total Cost Reserve Fund �!)C's Debt Financing Grants Other Tax Levy
Expenditures
Parks& Recreation $475,0001 $410,000 $0 $0 $0 $0 $65,000
$475,0001 $410,000 $0 $0 $0 $0 $65,000
Financing
Capital Item Capital Item No. ITotal Cost I Reserve Fund I DC's IDebt Financing IGrants 10ther ITax Levy IPage Reference
East Pier Rehabilitation PR-11 $50,OOO1 $50,000 $0 $0 $0 $0 $0 301
Utility Corridor Repairs PR-04 $125,000 $125,000 $0 $0 $0 $0 $0 294
Eden Pavilion PR-09 $100,000 $100,000 $0 $0 $0 $0 $0 299
Port Burwell Ball Diamond PR-05 $200,000 $135,000 $0 $0 $0 $0 $65,000 295
$475,000 $410,000 $0 $0 $0 $0 $65,000
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2307 Trail Reserve $171,680 $10,000 $125,000 $56,680
2318 Parks & Playground Reserve $195,000 $0 $185,000 $10,000
2350 Parkland Reserve $213,143 $0 $165,000 $48,143
2369 Vienna Reserve Fund 1 $294,955 $0 $0 $294,955
Municipality of Bayham
Parks & Recreation -2027
Financing
Total Cost Reserve Fund �13C's Debt Financing Grants Other Tax Levy
Expenditures
Parks & Recreation $720,000 $0 $0 $0 $225,000 $0 $495,000
$720,000 $0 $0 $0 $225,000 $0 $495,000
Financing
Capital Item Capital Item No. Total Cost I Reserve Fund DC's I Debt Financing I Grants 10ther ITax Levy JPage Reference
Beach Accessibility PR-13 $50,000 $0 $0 $0 $50,000 $0 $0 303
Richmond Pavilion PR-10 $65,000 $0 $0 $0 $0 $0 $65,000 300
East Pier Rehabilitation PR-11 $275,000 $0 $0 $0 $0 $0 $275,000 301
Straffordville Ball Diamond PR-08 $250,000 $0 $0 $0 $175,000 $0 $75,000 298
Beach Shade Structure I PR-03 1 $80,000 $0 $0 $0 $0 $0 $80,000 293
$720,000 $0 $0 $0 $225,000 $0 $495,000
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
2307 Trail Reserve $56,680 $10,000 $0 $66,680
2318 Parks & Playground Reserve $10,000 $0 $0 $10,000
2350 Parkland Reserve $48,143 $0 $0 $48,143
2369 Vienna Reserve Fund $294,955 $0 $0 $294,955
Municipality of Bayham
Parks & Recreation -2028
Financing
Total Cost Reserve Fund FDC's Debt Financing Grants Other Tax Levy
Expenditures
Parks& Recreation $380,000 $0 $0 $0 $300,0001 $0 $80,000
$380,000 $0 $0 $0 $300,0001 $0 $80,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Playground Equipment PR-02 $90,000 $0 $0 $0 $90,000 $0 $0 292
Memorial Park Pavilion PR-12 $250,000 $0 $0 $0 $210,000 $0 $40,000 302
Quality of Place Banners PR-01 $40,000 $0 $0 $0 $0 $0 $40,000 291
$380,000 $0 $0 $0 $300,000 $0 $80,000
Budgeted Reserve Balance Opening Closing
Acc No. Acc. Name Balance Transfer to Transfer from Balance
2307 Trail Reserve $66,680 $10,000 $0 $76,680
2318 Parks & Playground Reserve $10,000 $0 $0 $10,000
2350 Parkland Reserve $48,143 $0 $0 $48,143
2369 Vienna Reserve Fund $294,955 $0 $0 $294,955
Municipality of Bayham
Parks & Recreation -2029
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Parks & Recreation $110,000 $0 $0 $0 $90,000 $0 $20,000
$110,000 $0 $0 $0 $90,000 $0 $20,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Playground Equipment PR-02 $90,000 $0 $0 $0 $90,000 $0 $0 292
Electric Charging Station PR-06 $20,000 $0 $0 $0 $0 $0 $20,000 296
$110,000 $0 $0 $0 $90,000 $0 $20,000
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2307 Trail Reserve $76,6801 $10,000 $0 $86,680
2318 Parks & Playground Reserve $10,000 $0 $0 $10,000
2350 Parkland Reserve $48,143 $0 $0 $48,143
2369 Vienna Reserve Fund $294,955 $0 $0 $294,955
Municipality of Bayham
Parks & Recreation -2030
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Parks& Recreation $90,000 $0 $01 $0 $90,000 $01 $0
$90,000 $0 $0 $0 $90,000 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Playground Equipment PR-02 $90,000 $0 $0 $0 $90,000 $0 $0 292
$90,000 11 $0 $0 $0 $90,000 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
2307 Trail Reserve $86,680 $10,000 $0 $96,680
2318 Parks & Playground Reserve $10,000 $0 $0 $10,000
2350 Parkland Reserve $48,143 $0 $0 $48,143
2369 Vienna Reserve Fund 1 $294,955 $0 $0 $294,955
Municipality of Bayham
Parks & Recreation -2031
Financing
Total Cost Reserve Fund DC's JDebt Financing Grants Other Tax Levy
Expenditures
Parks & Recreation $90,000 $0 $0 $0 $90,000 $0 $0
$90,000 $0 $0 $0 $90,000 $0 $0
Financing
Capital Item I Capital Item No. Total Cost Reserve Fund DC's IDebt Financing Grants Other Tax Levy Page Reference
Playground Equipment PR-02 $90,000 $0 $0 $0 $90,000 $0 $0 292
$90,000 $0 $01 $0 $90,000 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2307 Trail Reserve $96,680 $10,000 $0 $106,680
2318 Parks & Playground Reserve $10,000 $0 $0 $10,000
2350 Parkland Reserve $48,143 $0 $0 $48,143
2369 Vienna Reserve Fund 1 $294,9551 $0 $0 $294,955
Municipality of Bayham
Parks & Recreation -2032
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Parks & Recreation $90,000 $0 $0 $0 $90,000 $0 $0
$90,000 $0 $0 $0 $90,000 $0 $0
Financing
Capital Item I Capital Item No. Total Cost Reserve Fund DC's IDebt Financing Grants Other Tax Levy Page Reference
Playground Equipment PR-02 $90,000 $0 $0 $0 $90,000 $0 $0 292
$90,000 $0 $0 $0 $90,000 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2307 Trail Reserve $106,680 $10,000 $0 $116,680
2318 Parks & Playground Reserve $10,000 $0 $0 $10,000
2350 Parkland Reserve $48,143 $0 $0 $48,143
2369 Vienna Reserve Fund 1 $294,9551 $0 $0 $294,955
Municipality of Bayham
Parks & Recreation -2033
Financing
Total Cost Reserve Fund DC's JDebt Financing Grants Other Tax Levy
Expenditures
Parks & Recreation $90,000 $0 $0 $0 $90,000 $0 $0
$90,000 $0 $0 $0 $90,000 $0 $0
Financing
Capital Item I Capital Item No. Total Cost Reserve Fund DC's IDebt Financing Grants Other Tax Levy Page Reference
Playground Equipment PR-02 $90,000 $0 $0 $0 $90,000 $0 $0 292
$90,000 $0 $01 $0 $90,000 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2307 Trail Reserve $116,680 $10,000 $0 $126,680
2318 Parks & Playground Reserve $10,000 $0 $0 $10,000
2350 Parkland Reserve $48,143 $0 $0 $48,143
2369 Vienna Reserve Fund 1 $294,9551 $0 $0 $294,955
Municipality of Bayham
Parks & Recreation -2034
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Parks & Recreation $90,000 $0 $0 $0 $90,000 $0 $0
$90,000 $0 $0 $0 $90,000 $0 $0
Financing
Capital Item I Capital Item No. Total Cost Reserve Fund DC's IDebt Financing Grants Other Tax Levy Page Reference
Playground Equipment PR-02 $90,000 $0 $0 $0 $90,000 $0 $0 292
$90,000 $0 $0 $0 $90,000 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2307 Trail Reserve $126,680 $10,000 $0 $136,680
2318 Parks & Playground Reserve $10,000 $0 $0 $10,000
2350 Parkland Reserve $48,143 $0 $0 $48,143
2369 Vienna Reserve Fund 1 $294,9551 $0 $0 $294,955
Municipality of Bayham
Parks & Recreation -2035
Financing
Total Cost Reserve Fund DC's JDebt Financing Grants Other Tax Levy
Expenditures
Parks & Recreation $50,000 $0 $0 $0 $0 $0 $50,000
$50,000 $0 $0 $0 $0 $0 $50,000
Financing
Capital Item I Capital Item No. Total Cost Reserve Fund DC's IDebt Financing Grants Other Tax Levy Page Reference
Memorial Park Pav PR-07 $50,000 $0 $0 $0 $0 $0 $50,000 297
$50,000 $0 $0 $0 $0 $0 $50,000
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2307 Trail Reserve $136,680 $10,000 $0 $146,680
2318 Parks & Playground Reserve $10,000 $0 $0 $10,000
2350 Parkland Reserve $48,143 $0 $0 $48,143
2369 Vienna Reserve Fund 1 $294,9551 $0 $0 $294,955
Municipality of Bayham
Facilities 2026-2035
2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
Expenditures
Facilities $5,330,250 $185,000 $650,000 $25,000 $150,000 $25,000 $130,000 $0 $0 $0
$5,330,250 $185,000 $6505000 $25,000 $150,000 $25,000 $1305000 $0 $0 $0
Financing
Tax Levy $75,000 $185,000 $600,000 $0 $150,000 $0 $130,000 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grants $2,974,250 $0 $0 $0 $0 $0 $0 $0 $0 $0
Debt $1,389,000 $0 $0 $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Reserves $892,0001 $0 $50,0001 $25,000 $0 $25,000 $0 $0 $0 $0
$5,330,250 $1855000 $65050001 $25,0001 $150,0001 $25,0001 $130,000 $0 $0 $0
Municipality of Bayham
Facilities -2026
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Facilities $5,330,2501 $892,0001 $0 $1,389,0001$2,974,2501 $0 $75,000
� $5,330,2501 $892,0001 $0 $1,389,0001$2,974,2501 $0 $75,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Facility Audit FA-02 $60,000 $60,000 $0 $0 $0 $0 $0 305
SCC Expansion FA-04 $3,614,000 $757,000 $0 $1,389,000 $1,468,000 $0 $0 307
PB Lighthouse FA-08 $1,506,250 $0 $0 $0 $1,506,250 $0 $0 311
PB East Beach Washroom Exg FA-09 $75,000 $75,000 $0 $0 $0 $0 $0 312
Marine Museum PL FA-11 $75,000 $0 $01 $0 $0 $0 $75,000 314
$5,330,2501 $892,0001 $0 $1,389,0001$2,974,250 $0 $75,000
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2336 Facilities Reserve $848,491 $40,000 $791,663 $96,828
2360 SCC Reserve $2,346 $0 $2,208 $138
2364 SCC Capital Donations Reserve $48,129 $0 $48,129 $0
2326 Museums General $2,238 $0 $0 $2,238
2322 Lighthouse 1 $53,479 $0 $0 $53,479
Municipality of Bayham
Facilities -2027
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Facilities $185,000 $0 $0 $0 $0 $0 $185,000
$185,000 $0 $0 $0 $0 $0 $185,000
Financing
Capital Item I Capital Item No. ITotal Cost I Reserve Fund I DC's IDebt Financing IGrants 10ther ITax Levy I Page Reference
PW Yard Wash Bay I FA-07 $125,000 $0 $0 $0 $0 $0 $125,000 310
Straffordville Fire Hall Generator I FA-05 $60,000 $0 $0 $0 $0 $0 $60,000 308
$185,000 $0 $0 $0 $0 $0 $185,000
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
2336 Facilities Reserve $96,828 $40,000 $0 $136,828
2360 SCC Reserve $138 $0 $0 $138
2364 SCC Capital Donations Reserve $0 $0 $0 $0
2326 Museums General $2,238 $0 $0 $2,238
2322 Lighthouse 1 $53,479 $0 $0 $53,479
Municipality of Bayham
Facilities -2028
Financing
Total Cost Reserve Fund DC's �DebtFinancing Grants Other Tax Levy
Expenditures
Facilities $ 650,000 1 $ 50,000 1 $01 $0 $0 $0 $600,000
$ 650,000 1 $ 50,000 1 $ - $ - 1 $ - $ - $ 600,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
PB Beach Washroom Expansic FA-09 $500,000 $0 $0 $0 $0 $0 $500,000 312
Straffordville Parking Lot FA-03 $50,000 $50,000 $0 $0 $0 $0 $0 306
PW Saltdome Cover and Back FA-10 $100,000 $0 $0 $0 $0 $0 $100,000 313
$650,0001 $50,000 $0 $0 $0 $0 $600,000
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2336 Facilities Reserve $136,828 $40,000 $50,000 $126,828
2360 SCC Reserve $138 $0 $0 $138
2364 SCC Capital Donations Reserve $0 $0 $0 $0
2326 Museums General $2,238 $0 $0 $2,238
2322 Lighthouse $53,479 $0 $0 $53,479
Municipality of Bayham
Facilities-2029
Financing
Total Cost Reserve Fund IDC's I Debt Financing Grants Other I Tax Levy
Expenditures
Facilities $25,000 $25,000 $0 $0 $0 $0 $0
$25,0001 $25,000 1 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Straff Library Ramp FA-14 $25,000 $25,000 $0 $0 $0 $0 $0 317
$25,000 $25,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2336 Facilities Reserve $126,828 $40,000 $0 $166,828
2360 SCC Reserve $138 $0 $0 $138
2364 SCC Capital Donations Reserve $0 $0 $0 $0
2326 Museums General 1 $2,238 $0 $0 $2,238
2322 Lighthouse 1 $53,479 $0 $0 $53,479
Municipality of Bayham
Facilities -2030
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Facilities I $150,000 $0 $0 $0 $0 $0 $150,000
$150,000 $0 $0 $0 $0 $0 $150,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
SCC Parking Lot FA-01 $150,000 $150,000 304
$150,000 $0 $0 $0 $0 $0 $150,000
Budgeted Reserve Balance Opening Closing
Acc No. Acc. Name Balance Transfer to Transfer from Balance
2336 Facilities Reserve $166,828 $40,000 $0 $206,828
2360 SCC Reserve $138 $0 $0 $138
2364 SCC Capital Donations Reserve $0 $0 $0 $0
2326 Museums General $2,238 $0 $0 $2,238
23221 Lighthouse 1 $53,479 $0 $0 $53,479
Municipality of Bayham
Facilities -2031
117
Financing
Total Cost Reserve Fund DC's FDebtFinancing Grants Other Tax Levy
Expenditures
Facilities 1 $25,0001 $25,000 $0 $0 $0 $0 $0
$25,0001 $25,000 $0 $0 1 $0 $0 $0
Financing
Capital Item lCapital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
PB Library Roof FA-13 $25,000 $25,000 $0 $0 $0 $0 $0 316
$25,000 $25,000 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2336 Facilities Reserve $206,828 $40,000 $25,000 $221,828
2360 SCC Reserve $138 $0 $0 $138
2364 SCC Capital Donations Reserve $0 $0 $0 $0
2326 Museums General $2,238 $0 $0 $2,238
2322 Lighthouse $53,479 $0 $0 $53,479
Municipality of Bayham
Facilities -2032
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Facilities $130,000 $0 $0 $0 $0 $0 $130,000
$130,000 $0 $0 $0 $0 $0 $130,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
PW Generator FA-06 $60,000 $0 $0 $0 $0 $0 $60,000 309
SCC Generator FA-12 $70,000 $0 $0 $0 $0 $0 $70,000 315
$130,000 $0 $0 $0 $0 $0 $130,000
Budgeted Reserve Balance Opening
Acc No. jAcc. Name Balance Transfer to Transfer from Closing Balance
2336 Facilities Reserve $221,828 $40,000 $0 $261,828
2360 SCC Reserve $138 $0 $0 $138
2364 SCC Capital Donations Reserve $0 $0 $0 $0
2326 Museums General $2,238 $0 $0 $2,238
2322 Lighthouse $53,479 $0 $0 $53,479
Municipality of Bayham
Facilities -2033
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Facilities $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
Financing
Capital Item I Capital Item No. Total Cost IReserveFund DC's I Debt Financing Grants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2336 Facilities Reserve $261,828 $40,000 $0 $301,828
2360 SCC Reserve $138 $0 $0 $138
2364 SCC Capital Donations Reserve $0 $0 $0 $0
2326 Museums General $2,238 $0 $0 $2,238
2322 Lighthouse $53,479 $0 $0 $53,479
Municipality of Bayham
Facilities -2034
Financing
Total Cost Reserve Fund DC's �DebtFinancing Grants Other Tax Levy
Expenditures
Facilities 1 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
Financing
Capital Item lCapital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2336 Facilities Reserve $301,828 $40,000 $0 $341,828
2360 SCC Reserve $138 $0 $0 $138
2364 SCC Capital Donations Reserve $0 $0 $0 $0
2326 Museums General $2,238 $0 $0 $2,238
2322 Lighthouse $53,479 $0 $0 $53,479
Municipality of Bayham
Facilities -2035
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Facilities 1 $01 $01 $01 $01 $01 $01 $0
$0 $0 $0 $0 $0 $0 $0
Financing
Capital Item lCapital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy IPageReference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening
Acc No. Acc. Name Balance Transfer to Transfer from Closing Balance
2336 Facilities Reserve $341,828 $40,000 $0 $381,828
2360 SCC Reserve $138 $0 $0 $138
2364 SCC Capital Donations Reserve $0 $0 $0 $0
2326 Museums General $2,238 $0 $0 $2,238
2322 Lighthouse $53,479 $0 $0 $53,479
Municipality of Bayham
Planning & Development 2026-2035
2026 1 2027 1 2028 1 2029 2030 2031 2032 2033 2034 2035
Expenditures
Planning & Development $45,000 $25,000 $0 $0 $40,000 $15,000 $35,000 $0 $30,000 $45,000
$45,000 $25,000 $0 $0 $40,000 $15,000 $35,000 $0 $30,000 $45,000
Financing
Tax Levy $0 $25,000 $0 $0 $40,000 $15,000 $35,000 $0 $30,000 $45,000
Development Charges $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Reserves $45,000 $0 $0 $0 $0 $0 $0 $0 $0 $0
$45,000 $25,000 $0 $0 $40,000 $15,000 $35,000 $0 $30,000 $45,000
Municipality of Bayham
Planning & Development -2026
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Planning & Development 1 $45,0001 $45,000 $0 $0 $01 $01 $0
$45,0001 $45,000 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund I DC's I Debt Financing Grants Other Tax Levy Page Reference
Zoning By-law Review PD-02 $45,000 $45,000 $0 $0 $0 $0 $0 319
$45,000 $45,000 $01 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
23631 Planning & Development Reserve 1 $28,064 $0 $45,000 -$16,936
Municipality of Bayham
Planning & Development - 2027
Financing
Total Cost Reserve Fund IDC's I Debt Financing Grants Other I Tax Levy
Expenditures
Planning & Development 1 $25,000 $0 $01 $0 $0 $0 $25,000
$25,000 $0 $0 $0 $0 $0 $25,000
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's I Debt Financing I Grants Other Tax Levy Page Reference
Zoning By-law ReviE PD-02 $25,000 $0 $0 $0 $0 $0 $25,000 319
$25,000 $0 1 $0 1 $0 1 $0 $0 $25,000
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
23631 Planning & Development Reserve -$16,936 $0 $0 -$16,936
Municipality of Bayham
Planning & Development -2028
Financing
Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy
Expenditures
Planning & Development $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $01 0
Financing
Capital Item I Capital Item No. ITotal Cost Reserve Fund DC's I Debt Financing I Grants 10ther ITax Levy Page Reference
1 $o $01 $o $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name I Balance Transfer to Transfer from Balance
23631 Planning & Development Reserve -$16,936 $0 $0 -$16,936
Municipality of Bayham
Planning & Development -2029
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other Tax Levy
Expenditures
Planning & Development $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost lReserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. jAcc. Name Balance Transfer to Transfer from Balance
23631 Planning & Development Reserve 1 -$16,936 $0 $0 -$16,936
Municipality of Bayham
Planning & Development-2030
Financing
Total Cost Reserve Fund DC's �DebtFinancing Grants Other Tax Levy
Expenditures
Planning& Development $40,000 $0 $0 $0 $0 $0 $40,0100
$40,000 $0 1 $0 $0 1 $0 1 $0 1 $40,000
Financing
Capital Item I Capital Item No. Total Cost IReserve Fund DC's I Debt Financing Grants Other Tax Levy Page Reference
Official Plan Review PD-03 $40,000 $0 $0 $0 $0 $0 $40,000 320
$40,000 $0 $0 $0 $0 $0 $40,000
Budgeted Reserve Balance I Opening
Acc No. jAcc. Name I Balance Transfer to Transfer from Closing Balance
23631 Planning & Development Reserve 1 -$16,936 $0 $0 -$16'936
Municipality of Bayham
Planning & Development -2031
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other I Tax Levy
Expenditures
Planning & Development $15,000 $0 $0 $0 $0 $0 $15,000
$15,000 $0 $0 $0 $0 $0 $15,000
Financing
Capital Item Capital Item No. Total Cost IReserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Official Plan Review I PD-03 $15,000 $0 $0 $0 $0 $0 $15,000 320
$15,000 $0 $0 $0 $0 $0 $15,000
Budgeted Reserve Balance Opening Closing
Acc No. IAcc. Name Balance Transfer to Transfer from Balance
23631 Planning & Development Reserve -$16,936 $0 $0 -$16,936
Municipality of Bayham
Planning & Development -2032
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other I Tax Levy
Expenditures
Planning & Development $35,000 $0 $0 $0 $0 $0 $35,000
$35,000 $0 $0 $0 $0 $0 $35,000
Financing
Capital Item Capital Item No. Total Cost IReserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
Zoning By-law Review I PD-04 $35,000 $0 $0 $0 $0 $0 $35,000 321
$35,000 $0 $0 $0 $0 $0 $35,000
Budgeted Reserve Balance Opening Closing
Acc No. IAcc. Name Balance Transfer to Transfer from Balance
23631 Planning & Development Reserve -$16,936 $0 $0 -$16,936
Municipality of Bayham
Planning & Development -2033
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other I Tax Levy
Expenditures
Planning & Development $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
Financing
Capital Item Capital Item No. Total Cost Reserve Fund DC's Debt Financing Grants Other Tax Levy Page Reference
$0
$0 $0 $0 $0 $0 $0 $0
Budgeted Reserve Balance Opening Closing
Acc No. IAcc. Name Balance Transfer to Transfer from Balance
23631 Planning & Development Reserve -$16,936 $0 $0 -$16,936
Municipality of Bayham
Planning & Development -2034
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other I Tax Levy
Expenditures
Planning & Development $30,000 $0 $0 $0 $0 $0 $30,000
$30,000 $0 $0 $0 $0 $0 $30,000
Financing
Capital Item Capital Item No. Total Cost IReserve Fund DC's I Debt Financing Grants Other Tax Levy Page Reference
Official Plan Review PD-01 $30,000 $0 $0 $0 $0 $0 $30,000 318
$30,000 $0 $0 $0 $0 $0 $30,000
Budgeted Reserve Balance Opening Closing
Acc No. IAcc. Name Balance Transfer to Transfer from Balance
23631 Planning & Development Reserve -$16,936 $0 $0 -$16,936
Municipality of Bayham
Planning & Development -2035
Financing
Total Cost Reserve Fund �DC's Debt Financing Grants Other I Tax Levy
Expenditures
Planning & Development $45,000 $0 $0 $0 $0 $0 $45,000
$45,000 $0 $0 $0 $0 $0 $45,000
Financing
Capital Item Capital Item No. Total Cost IReserve Fund DC's I Debt Financing Grants Other Tax Levy Page Reference
Official Plan Review PD-01 $45,000 $0 $0 $0 $0 $0 $45,000 318
$45,000 $0 $0 $0 $0 $0 $45,000
Budgeted Reserve Balance Opening Closing
Acc No. IAcc. Name Balance Transfer to Transfer from Balance
23631 Planning & Development Reserve -$16,936 $0 $0 -$16,936
g,AYHA�l
Municipality of Bayham
Capital Information Sheet
O'oPortanity IsYov'Se
Year: 12027 1 Capital Item No. GG-01
Department: I General Government
Capital Project Item: I Market Analysis
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement I X Other
escrip ion
Pursuant to the Municipality of Bayham Personnel Policy Manual Compensation Philosophy
Capital Budget -Total Project Cost $60,000
Year 1 $20,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $20,000 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $20,000
Capital Budget - Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $20,000 $0 $0 $0 $20,000 $0 $0
Total 1 $20,000 0 0 $0 $20,000 0 $0
Expected Useful Life of the Asset (Years) 14
g,AYHA�l
Municipality of Bayham
Capital Information Sheet
O'oPortanity IsYov'Se
Year: 12027 1 Capital Item No. GG-02
Department: I General Government
Capital Project Item: I Strategic Plan Update
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement I X Other
escrip ion
Update of existing Strategic Plan for new Council term
Capital Budget -Total Project Cost $90,000
Year 1 $30,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $30,000 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $30,000
Capital Budget - Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $30,000 $0 $0 $0 $30,000 $0 $0
Total 1 $30,000 0 0 0 30,000 0 0
Expected Useful Life of the Asset (Years) 14
g,AYHA.1lT
Municipality of Bayham
Capital Information Sheet
�PPoi't+nity IsYoJt�
Year: 12026 1 Capital Item No. GG-03
Department: I General Government
Capital Project Item: I Council Computers
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Council laptop replacement for new term of Council
Capital Budget -Total Project Cost $30,000
Year 1 $10,0001 Year 4 $0 Year 7 $0
Year 2 $01 Year 5 $10,000 Year 8 $0
Year 3 $01 Year 6 $0 Year 9 $10,000
Capital Budget - Financing I Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $10,000 $0 $0 $0 $10,000 $0 $0
Total 1 $10,000 $0 $0 $0 $10,000 $0 $0
Expected Useful Life of the Asset (Years) 14
g,AYHA.1lT
Municipality of Bayham
Capital Information Sheet
�PPoi't+nity IsYoJt�
Year: 12028 Capital Item No. GG-04
Department: I General Government
Capital Project Item: I Website Redevelopment
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement X Other
Description
Update website development for increased service.
Capital Budget -Total Project Cost $50,000
Year 1 $25,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $25,000 Year 9 $0
Capital u get- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $25,000 $0 $0 $0 $0 $25,000 $0
Total 1 $25,000 0 0 0 $0 $25,000 0
Expected Useful Life of the Asset(Years) I n/a
g,AYHA.1lT
Municipality of Bayham
Capital Information Sheet
�PPoi't+nity IsYoJt�
Year: 12030 1 Capital Item No. GG-05
Department: I General Government
Capital Project Item: I Development Charges Study
Capital Project Priority
Health & Safety Issue X Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement X Other
escrip ion
Lower-tier development charge study to help fund future capital needs with growth development (stormwater,
SAR, Parks/Rec, Fire, Library, Roads)
Capital Budget-Total Project Cost $25,000
Year 1 $25,000 Year 4 0 Year 7 0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital u get - Financing Year 1 Year 2 Year 3 1Year 4 Year 5 1 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $25,000 $0 $0 $0 $0 $0 $0
Total 25,000 0 $0 $0 $01 $0 0
Expected Useful Life of the Asset(Years) I n/a
gAYHA11?
Municipality of Bayham
"l
Capital Information Sheet
�'�Aol.tunity Is'`t �e,
Year: 12026 1 Capital Item No. FD-01
Department: I Fire
Capital Project Item: Bunker Gear
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Bunker Gear is requied to be replaced every 10 years under the NFPA Standards. With some 40 -45 firefighters,
this means 4.5 sets of bunker gear a year at a current cost of$3300 per set. The Municipality is working with other
Municipalities in the County to Bulk Purchase.
Capital Budget -Total Project Cost $172,000
Year 1 $16,000 Year 4 $17,000 Year 7 $18,000
Year 2 $16,000 Year 5 $17,000 Year 8 $18,000
Year 3 $17,000 Year 6 $17,000 Year 9 $18,000
Year 10 $18,000
Capital Budget - Financing I ear 1 1 Year 2 Year 3I Year 4 Year 5 1 Year 6 Year 7
Tax Levy $16,000 $16,000 $17,000 $17,000 $17,000 $17,000 $18,000
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $T6-,0001 $16,0001 $17,000 $17,0001 $17,0001 $17,0001 $18,000
Expected Useful Life of the Asset(Years) 120
4,AYH�
Municipality of Bayham
�APoliunity Is�o�{�e
Capital Information Sheet
Year: 12026 1 Capital Item No. FD-02
Department: Fire
Capital Project Item: Portable Radios
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy - Environmental Susi Service Enhancement
Efficiency & Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Hortable Radios are a neccesi y in every call. I ec no ogy is driving change. We are currently using
radios that the manufacturer will no longer service and our latest model, is said to be stopped
manufacturing in less than 1 years. Curent Radios are at a cost of$1,800. When obtaining the new
radios, a bank chara'na system will be reau'red est. $3000,
Capital Budget - Total Project Cost 1$79,000
Year 1 $6,000 Year 4 $8,000 Year 7 $8,000
Year 2 $7,500 Year 5 $8,000 Year 8 $8,000
Year 3 $7,500 Year 6 $8,000 Year 9 $9,000
Year 10 $9,000
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $6,000 $7,500 $7,500 $8,000 $8,000 $8,000 $8,000
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $6,0001 $7,5001 $7,500 $8,0001 $8,0001 $8,0001 $8,000
Expected Useful Life of the Asset (Y 10
gAYHA11?
Municipality of Bayham
"l
Capital Information Sheet
�'�Aol.tunity Is'`t �e,
Year: 12026 1 Capital Item No. FD-03
Department: Fire
Capital Project Item: Thermal Imagining Cameras
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Thermal Imaging Cameras are an absolute necessity in fire fighter safety and fire operations. The current devices
are aging and beginning to fail resulting in costly repairs for outdated equipment. The fire department currently
has 3 and should have 5.
Capital Budget -Total Project Cost $29,800
Year 1 $7,250 Year 4 $0 Year 7 $0
Year 2 $15,000 Year 5 $0 Year 8 $0
Year 3 $7,550 Year 6 $0 Year 9 $0
Year 10 $0
Capital Budget - Financing I ear 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $7,250 $15,000 $7,550 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total j T7,2501 $15,0001 $7,550 $0 $0 $0 $0
Expected Useful Life of the Asset(Years) 110
gAYHA11?
Municipality of Bayham
"l
Capital Information Sheet
�'�Aol.tunity Is'`t �e,
Year: 12027 1 Capital Item No. FD-04
Department: Fire
Capital Project Item: Fire Hose Replacement
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Fire Hose is a lite sattey piece ot equipment. Most ot trie nose can be clated to trie arrival ot tne trucK triatis trie
what would be considered noral replacement unless damaged during use or failed during annual testing. The
hose was not replaced due to economic pressures, however, needs to be replaced for the latest pumper and
tanker
Capital Budget -Total Project Cost $96,500
Year 1 $14,000 Year 4 $12,500 Year 7 $14,000
Year 2 $14,000 Year 5 $0 Year 8 $14,000
Year 3 $14,000 Year 6 $14,000 Year 9
Year 10
Capital Budget - Financing I ear 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $14,000 $14,000 $14,000 $12,500 $0 $14,000 $14,000
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $T4,0001 $14,0001 $14,000 $12,500 $0 $14,0001 $14,000
Expected Useful Life of the Asset(Years) 120
gAYHA11?
Municipality of Bayham
�PPol.tu IsYo4SQ'
Capital Information Sheet
nity
Year: 12027 1 Capital Item No. FD-05
Department: Fire
Capital Project Item: Ice Water Rescue Suits
Capital Project Priority
X Health & Safety Issue X Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
escrip ion
Ice Water Rescue Suits
Capital Budget-Total Project Cost $6,000
Year 1 $6,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Year 10 $0
Capital Budget - Financing Year 1 1 Year 2 Year 3 I Year 4 Year 5 1 Year 6 Year 7
Tax Levy $6,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $6,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHAIIT
Municipality of Bayham
Capital Information Sheet
�PPoi'tunity IsYo4S�
Year: 12026 Capital Item No. FD-06
Department: Fire
Capital Project Item: Tanker 1
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replaces the 1999 Superior unit currently in service. Projected life span of a tanker is currently set at 25 years.
This is over the NFPA recommendation of 20 years for tankers. The cost of maintaining the apparatus will be
monitored to ensure it wouldn't be prudent to replace the unit earlier and/or later. Operating safety will be part of
the assessment.
Capital Budget-Total Project Cost $680,000
Year 1 $680,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $680,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $680,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset(Years) 1 25
-%XXHA 41r
Municipality of Bayham
Capital Information Sheet
OppO—Unity_t"Y0 Pe,
Year: 12032 1 Capital Item No. FD-07
Department: Fire
Capital Project Item: Tanker 2
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replacement for the 2002 Superior Tanker currently in service. Projected life span of tankers is 25 years. This is
over the NFPA recommendations of 20 years for tankers. The cost of maintaining the apparatus will be monitored to
ensure it wouldn't be prudent to replace the unit earlier and/or later. Operating safety will be part of the review.
Capital Budget-Total Project Cost $1,000,000
Year 1 $1,000,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $775,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $225,000 $0 $0 $0 $0 $0 $0
Total 1 $1,000,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset(Years) 25
gAYHA11?
Municipality of Bayham
"l
Capital Information Sheet
�'�Aol.tunity Is'`t �e,
Year: 12028 1 Capital Item No. FD-08
Department: Fire
Capital Project Item: Command Vehicle
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Ten year replacement for the Silverado Command One pickup truck.
Capital Budget -Total Project Cost $65,000
Year 1 $65,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget - Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $65,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $65,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset(Years) 10
g,AYHA11?
Municipality of Bayham
Capital Information Sheet
�PPos'tunity_ZSY0Jtg
Year: 12029 1 Capital Item No. FD-09
Department: Fire
Capital Project Item: Pumper 2
Capital Project Priority
Health &Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Replaces the 2009 Rosenbauer unit currently in service. Projected life span of a pumper is currently set at 20
years. This is over the NFPA recommendation of 10 years for pumpers. The cost of maintaining the apparatus will
be monitored to ensure it wouldn't be prudent to replace the unit earlier and/or later. Operating safety will be part of
the assessment.
Capital Budget -Total Project Cost $1,000,000
Year 1 $1,000,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $775,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $225,000 $0 $0 $0 $0 $0 $0
Total 1 $1,000,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 1 20
-ONM 4
Municipality of Bayham
O �
Capital Information Sheet
APortunity I9 0
Year: 12026 1 Capital Item No. FD-10
Department: IFire
Capital Project Item: Radio System - Reserve
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy - Environmental Sust Service Enhancement
X Efficiency & Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Elgin County Fire Chiets recently completed a third party review ot the Communications Equipment
jointly owned by the municipalities. In the review, the equipment was deemed working effectively
however a strong recommendation for every department to start a reserve fund of $30,000. After
speakina with the other cheifs it was recommended startin in 2024.
Capital Budget - Total Project Cost $120,000
Year 1 $30,000 Year 4 $30,000 Year 7 $0
Year 2 $30,000 Year 5 $0 Year 8 $0
Year 3 $30,000 Year 6 $0 Year 9 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $30,000 $30,000 $30,000 $30,000 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $30,0001 $30,0001 $30,0001 $30,000 $0 $0 $0
Expected Useful Life of the Asset (Ye N/A
gAYHA11?
Municipality of Bayham
�PPol.tu IsYo4SQ'
Capital Information Sheet
nity
Year: 12032 1 Capital Item No. FD-11
Department: I Fire
Capital Project Item: Extrication Tools
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Extrication tools,jaws of life and other replacements.
Capital Budget -Total Project Cost $60,000
Year 1 $60,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9
Year 10
Capital Budget - Financing Year 1 Year 2 Year 3 11 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $60,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total $60,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset(Years) 120
.�►,AYHA�.
Municipality of Bayham
Capital Information Sheet
�f'Portunity IS 0
Year: 12027 1 Capital Item No. B-01
Department: I Building/ By-law Enforcement
Capital Project Item: I Pick-Up Truck
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy - Environmental Sustainabi Service Enhancement
Efficiency & Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Former CBO vehicle replacement (2017). Operating and maintenance costs will be monitored to determine
replacement.
Capital Budget - Total Project Cost $55,000
Year 1 $55,0001 Year 4 $0 IYear 7 1 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 IYear 9 1 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $55,000 $0 $0 $0 $0 $0 $0
Total 55,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 110
g,AYHA11?
Municipality of Bayham
o {
Capital Information Sheet
�'�Po='runity IsY �$
Year: 12026 1 Capital Item No. PW-01
Department: Public Works
Capital Project Item: Road Side Brushing
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Capital Budget -Total Project Cost $515,000
Year 1 $65,000 Year 4 $50,000 Year 7 $50,000
Year 2 $50,000 Year 5 $50,000 Year 8 $50,000
Year 3 $50,000 Year 6 $50,000 Year 9 $50,000
Capital Budget - Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $50,000 $50,000 $50,000 $50,000 $50,000 $50,000 $50,000
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $15,000 $0 $0 $0 $0 $0 $0
Total 1 $65,0001 $50,0001 $50,0001 $50,0001 $50,0001 $50,0001 $50,000
Expected Useful Life of the Asset(Years) I N/A
Municipality of Bayham
of
Capital Information Sheet
�'�Pol'tunity Is'Y O�
Year: 12026 1 Capital Item No. PW-02
Department: Public Works
Capital Project Item: Hill Management
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Improve draiange and road bed granular.
Capital Budget -Total Project Cost $330,000
Year 1 $60,000 Year 4 $30,000 Year 7 $30,000
Year 2 $30,000 Year 5 $30,000 Year 8 $30,000
Year 3 $30,000 Year 6 $30,000 Year 9 $30,000
Year 10 $30,000
Capital Budget - Financi7g---7 Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $30,000 $30,000 $30,000 $30,000 $30,000 $30,000 $30,000
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $30,000 $0 $0 $0 $0 $0 $0
Total 1 $60,0001 $30,0001 $30,0001 $30,0001 $30,0001 $30,0001 $30,000
Expected Useful Life of the Asset(Years) I N/A
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12032 1 Capital Item No. PW-03
Department: I Public Works
Capital Project Item: I Jackson Line West (4.4km)
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Jackson Line from Plank, west to dead end - road reconstruction including drainage improvements, granular road
base upgrades, double coat of tar and chip
Capital Budget -Total Project Cost $575,000
Year 1 $575,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $575,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 575,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12032 1 Capital Item No. PW-04
Department: I Public Works
Capital Project Item: I Tunnel Line (5.6km)
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Tunnel Line- pulverize surface, granular upgrades as required and resurface with a double coat of tar and chip
Capital Budget -Total Project Cost $325,000
Year 1 $325,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $325,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 325,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12032 1 Capital Item No. PW-05
Department: I Public Works
Capital Project Item: I Chute Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Chute Line. - granular upgrades, hill improvements, drainage upgrades, tree removal where required and surface
treatment with a double coat of tar and chip from Chapel St. to Tollgate Rd.
Capital Budget -Total Project Cost $230,000
Year 1 $230,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $230,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 230,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 115
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12032 1 Capital Item No. PW-06
Department: I Public Works
Capital Project Item: I Ottergate Line (2.7km)
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Ottergate Line- pulverize surface, granular upgrades as required and resurface with a double coat of tar and chip
Capital Budget -Total Project Cost $190,000
Year 1 $190,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $190,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 190,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
�p1YIiA�
Municipality of Bayham
Capital Information Sheet
�APoi.lvnity IsYo�s�
Year: 12026 1 Capital Item No. PW-07
Department: Public Works
Capital Project Item: Sidewalks
Capital Project Priority
X Health &Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness X Accessibility Improvement
X Asset Replacement Other
Description
Sidewalk Replacement-various villages and hamlets
Capital Budget-Total Project Cost $1,025,000
Year 1 $125,000 Year 4 $100,000 Year 7 $100,000
Year 2 $100,000 Year 5 $100,000 Year 8 $100,000
Year 3 $100,000 Year 6 $100,000 Year 9 $100,000
Capital Budget-Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $100,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $25,000 $0 $0 $0 $0 $0 $0
Total 1 $125,0001 $100,000 $100,000 $100,000 $100,0001 $100,000 $100,000
Expected Useful Life of the Asset(Years) 150
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12026 1 Capital Item No. PW-08
Department: I Public Works
Capital Project Item: I Road Signs
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement X Other
escrip ion
Road Sign Replacement
Capital Budget -Total Project Cost $90,000
Year 1 9,0001 Year 4 $9,000 Year 7 $9,000
Year 2 $9,0001 Year 5 $9,000 Year 8 $9,000
Year 3 $9,000 Year 6 $9,000 Year 9 $9,000
Year 10 9,000
Capital Budget- 1-inanciFg---T Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $9,000 $9,000 $9,000 $9,000 $9,000 $9,000 $9,000
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $9,0001 $9,00019,000 9,0001 $9,0001 $9,00019,000
Expected Useful Life of the Asset (Years) 15
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12026 1 Capital Item No. PW-09
Department: I Public Works
Capital Project Item: I Guardrails
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement X Other
escrip ion
Guardrail Replacement/Repair
Capital Budget -Total Project Cost $125,000
Year 1 $12,500 Year 4 $12,500 Year 7 $12,500
Year 2 $12,500 Year 5 $12,500 Year 8 $12,500
Year 3 $12,500 Year 6 $12,500 Year 9 $12,500
Year 10 12,500
Capital Budget- Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $12,500 $12,500 $12,500 $12,500 $12,500 $12,500 $12,500
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $12,5001 $12,500112,500 12,5001 $12,5001 $12,500112,500
Expected Useful Life of the Asset (Years) 120
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12032 1 Capital Item No. PW-10
Department: I Public Works
Capital Project Item: I Shady Lane (0.4km)
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Shady Lane - pulverize surface, granular upgrades as required and resurface with asphalt
Capital Budget -Total Project Cost $120,000
Year 1 $120,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $120,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 120,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-11
Department: I Public Works
Toll Gate Rd. and Black Bridge Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Tollgate Rd. and Black Bridge Line - granular upgrades, drainage upgrades, hill improvements, tree removal where
required and surface treatment with a double coat of tar and chip from Plank Rd. to heritage Line.
Capital Budget -Total Project Cost $250,000
Year 1 $250,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $250,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 250,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 115
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-12
Department: I Public Works
Somers Rd.
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Somers Rd. -granular upgrades, drainage upgrades, hill improvements, tree removal where required and surface
treatment with a double coat of tar and chip from Talbot Rd. to the dead end
Capital Budget -Total Project Cost $250,000
Year 1 $250,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 Year 7
Tax Levy $250,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 250,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 115
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-13
Department: I Public Works
Mitchell Rd.
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Mitchell Rd. -granular upgrades, drainage upgrades, hill improvements, tree removal where required and surface
treatment with a double coat of tar and chip from Jackson Line to Calton Line
Capital Budget -Total Project Cost $180,000
Year 1 $180,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 Year 7
Tax Levy $180,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 180,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 115
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12032 1 Capital Item No. PW-14
Department: I Public Works
Capital Project Item: I Backhoe
Capital Project Priority
Health & Safety Issue Growth Related Need
x Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replacement backhoe
Capital Budget -Total Project Cost $240,000
Year 1 $240,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 I Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $210,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $30,000 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 240,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 110
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-15
Department: I Public Works
Capital Project Item: I Ridge Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Ridge Line - granular upgrades, drainage upgrades, hill improvements, tree removal where required and surface
treatment with a double coat of tar and chip from Plank Rd. to Eden Line
Capital Budget -Total Project Cost $250,000
Year 1 $250,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 Year 7
Tax Levy $250,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 250,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 115
4,AYHA.1lT
Municipality of Bayham
Capital Information Sheet
OApo+'="unity IsY�Jt�
Year 12034 1 Capital Item No. PW-16
Department: I Public Works
Capital Project Item: I Tollgate Road Single
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
escrip ion
Single Tollgate Rd. Light Line to Heritage Line
Capital Budget-Total Project Cost $325,000
Year 1 $325,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $325,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 325,000 0 0 0 0 0 0
Expected Useful Life of the Asset(Years)
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12034 1 Capital Item No. PWA 7
Department: I Public Works
Capital Project Item: I Storm Water Facilities Maintenance
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Sediment Cleanout/Brush Control -Storm Retention Ponds
Capital Budget-Total Project Cost $75,000
Year 1 $75,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $75,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $75,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years)
Municipality of Bayham
r Capital Information Sheet
�AAorFunily IsY�tlS�
Year: 12026 1 Capital Item No. PW-18
Department: I Public Works
Capital Project Item: I Mower
Capital Project Priority
Health &Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Mower
Capital Budget-Total Project Cost $27,000
Year 1 $27,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Year 10
Capital u ge -Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $27,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 27,000 0 0 0 0 0 0
Expected Useful Life of the Asset(Years) 115
Municipality of Bayham
r Capital Information Sheet
�AAorFunily IsY�tlS�
Year: 12026 1 Capital Item No. PW-19
Department: I Public Works
Capital Project Item: I Gravel Road Program
Capital Project Priority
Health &Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Gravel Road Program - placement of A-gravel
Capital Budget-Total Project Cost $2,150,000
Year 1 $215,000 Year 4 $215,000 Year 7 $215,000
Year 2 $215,000 Year 5 $215,000 Year 8 $215,000
Year 3 $215,000 Year 6 $215,000 Year 9 $215,000
Year 10 -$215,000
Capital u ge -Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $215,000 $215,000 $215,000 $215,000 $215,000 $215,000 $215,000
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $215,0001 $215,0001215,000 215,0001 $215,0001 $215,0001215,000
Expected Useful Life of the Asset(Years) 115
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12026 1 Capital Item No. PW-20
Department: I Public Works
Capital Project Item: I Bridge & Culvert Inspections
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Ontario Structure Inspection Manual (OSIM) Inspections
Capital Budget -Total Project Cost $65,000
Year 1 $13,000 Year 4 $0 Year 7 $13,000
Year 2 $0 Year 5 $13,000 Year 8 $0
Year 3 $13,000 Year 6 $0 Year 9 $13,000
Capital Budget- Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $13,000 $0 $13,000 $0 $13,000 $0 $13,000
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $13,0001 $0113,000 01 $13,0001 $0113,000
Expected Useful Life of the Asset (Years) 12
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12027 1 Capital Item No. PW-21
Department: I Public Works
Capital Project Item: I Port Burwell Storm Sewer Phase 1 C-D
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Storm Sewer Master Plan Phase 1 C (Brock St.) and D (Erieus St. Brock St. -Wellington St)- Grant Dependent
Capital Budget -Total Project Cost $3,250,000
Year 1 $1,650,000 Year 4 $0 1 IYear 7 11 $0
Year 2 $1,600,000 Year 5 $0 Year 8 $0
Year 3 $01 Year 6 $0 1 IYear 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $1,650,000 $1,600,000 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $1,650,000 $1,600,000 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 180
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12028 1 Capital Item No. PW-22
Department: I Public Works
Capital Project Item: I Tollgate Road Single
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Single Tollgate Rd. Tunnel Line - Light Line
Capital Budget-Total Project Cost $85,000
Year 1 $85,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $85,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $85,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12033 1 Capital Item No. PW-23
Department: I Public Works
Capital Project Item: I Tunnel Line from County Rd.#55 to Plank Rd
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
resurface with a single tar and chip
Capital Budget -Total Project Cost $200,000
Year 1 $200,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $200,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 200,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 112
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12034 1 Capital Item No. PW-24
Department: I Public Works
Capital Project Item: I Pick-Up
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Replace 01-24 Pick-up
Capital Budget-Total Project Cost $70,000
Year 1 $70,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $70,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $70,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 110
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12026 1 Capital Item No. PW-25
Department: I Public Works
Capital Project Item: I Tandem
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replace Truck 3 (2012 Tandem)
Capital Budget -Total Project Cost $540,000
Year 1 $540,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $520,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $20,000 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 540,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 110
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12030 1 Capital Item No. PW-26
Department: I Public Works
Capital Project Item: I Pick-Up Trucks
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other-Trade-In $15,000
Description
Replace 07-20,14-20,17-20
Capital Budget-Total Project Cost $195,000
Year 1 $195,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 1 Year 5 1 Year 6 Year 7
Tax Levy $195,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $195,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 110
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12034 1 Capital Item No. PW-27
Department: I Public Works
Capital Project Item: I Vienna Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Single Tar& Chip
Capital Budget-Total Project Cost $220,000
Year 1 $220,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $220,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $220,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12034 1 Capital Item No. PW-28
Department: I Public Works
Capital Project Item: I Port Burwell Storm Sewer Phase 6
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Storm Sewer Master Plan Phase 6 (Addison St., Libbye St., Burwell St., Tennyson St., Southey St., Cowper St.,
Homer St.)
Capital Budget -Total Project Cost $3,600,000
Year 1 $3,600,000 Year 4 $0 1 IYear 7 11 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 IYear 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $3,600,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $3,600,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 180
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12026 1 Capital Item No. PW-29
Department: I Public Works
Capital Project Item: I Tandem
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replace Truck 4 (2015 Tandem)
Capital Budget -Total Project Cost $540,000
Year 1 $540,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $520,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $20,000 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 540,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 110
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12033 1 Capital Item No. PW-30
Department: I Public Works
Capital Project Item: I Maple Grove Line from Heritage Line to Plank Rd
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
resurface with a single tar and chip
Capital Budget -Total Project Cost $200,000
Year 1 $200,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $200,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 200,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 112
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12033 1 Capital Item No. PW-31
Department: I Public Works
Capital Project Item: I Springer Hill Rd. from Glencolin Rd to Pressey Rd
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
resurface with a single tar and chip
Capital Budget -Total Project Cost $170,000
Year 1 $170,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $170,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 170,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 112
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-32
Department: I Public Works
Capital Project Item: I Brown Rd.
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Brown Rd. - brush, ditch, culverts, granular and resurface with double coat tar and chip.
Capital Budget -Total Project Cost $200,000
Year 1 $200,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $200,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $200,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-33
Department: I Public Works
Capital Project Item: I Lakeshore Line Study
Capital Project Priority
X Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement X Other
Description
Lakeshore Line Study
Capital Budget -Total Project Cost $45,000
Year 1 $45,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $45,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $45,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 110
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12026 1 Capital Item No. PW-34
Department: I Public Works
Capital Project Item: I Best Line Culvert
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Best Line Culvert lining Eng 2026, 2027 Construction
Capital Budget -Total Project Cost $500,000
Year 1 $50,0001 Year 4 $0 Year 7 $0
Year 2 $450,000 Year 5 $0 Year 8 $0
Year 3 $01 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $50,000 $450,000 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $50,0001 $450,000 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 150
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12028 1 Capital Item No. PW-35
Department: I Public Works
Capital Project Item: I Grader
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replace Truck 6 (2011 Grader)
Capital Budget -Total Project Cost $800,000
Year 1 $800,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $750,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $50,000 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 800,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 115
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12027 1 Capital Item No. PW-36
Department: I Public Works
Capital Project Item: I Tandem
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replace Truck 8 (2016 Tandem)
Capital Budget -Total Project Cost $525,000
Year 1 $540,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
$520,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $20,000 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 540,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 110
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12026 1 Capital Item No. PW-37
Department: I Public Works
Capital Project Item: I Murray Rd.
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Murray Rd. - resurface with single coat tar and chip.
Capital Budget -Total Project Cost $72,000
Year 1 $72,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $72,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $72,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 115
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12027 1 Capital Item No. PW-38
Department: I Public Works
Capital Project Item: I Green Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Green Line. - brush, ditch, culverts, granular and resurface with double coat tar and chip.
Capital Budget -Total Project Cost $500,000
Year 1 $250,000 Year 4 $0 Year 7 $0
Year 2 $250,000 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 Year 7
Tax Levy $125,000 $125,000 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $125,000 $125,000 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $250,0001 $250,00010 0 0 0 0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12026 1 Capital Item No. PW-39
Department: I Public Works
Capital Project Item: I North St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
North St- resurface with asphalt King to Plank
Capital Budget -Total Project Cost $35,000
Year 1 $35,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $35,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $35,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12029 1 Capital Item No. PW-40
Department: I Public Works
Capital Project Item: I Port Burwell Storm Sewer Phase 1 E-F
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Storm Sewer Master Plan Phase 1 E-F (Pitt St.)
Capital Budget -Total Project Cost $2,990,000
Year 1 $2,990,000 Year 4 $0 1 IYear 7 11 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 IYear 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $2,990,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $2,990,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 180
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12027 1 Capital Item No. PW-41
Department: I Public Works
Capital Project Item: I Van Order Culvert
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Guardrails & End Treatments
Capital Budget -Total Project Cost $85,000
Year 1 $85,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $85,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $85,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 120
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12027 1 Capital Item No. PW-42
Department: I Public Works
Capital Project Item: I Tractor
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replace Truck 20 (2006 Tractor) including brusher
Capital Budget -Total Project Cost $300,000
Year 1 $300,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $280,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $20,000 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 300,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 115
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. PW-43
Department: I Public Works
Capital Project Item: I Pickup Truck
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
4x4 truck replacement
Capital Budget-Total Project Cost $60,000
Year 1 $60,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $55,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $5,000 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $60,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 110
4,AYHA.1lT
Municipality of Bayham
Capital Information Sheet
OApo+'="unity IsY�Jt�
Year: 12027 1 Capital Item No. PW-44
Department: I Public Works
Capital Project Item: I Pickup Truck
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replace Truck 2 (2007 Silverado)
Capital Budget-Total Project Cost $100,000
Year 1 $100,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $90,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $10,000 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 100,000 0 0 0 0 0 0
Expected Useful Life of the Asset(Years) 110
4,AYHA.1lT
Municipality of Bayham
Capital Information Sheet
OApo+'="unity IsY�Jt�
Year: 12027 1 Capital Item No. PW-45
Department: I Public Works
Capital Project Item: I Pickup Truck
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replace Truck 18 (2010 GMC)
Capital Budget-Total Project Cost $60,000
Year 1 $60,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $60,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 60,000 0 0 0 0 0 0
Expected Useful Life of the Asset(Years) 110
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. PW-46
Department: I Public Works
Capital Project Item: I Vac Unit
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Replace Truck 27 (2012 Vermeer Vac Unit)
Capital Budget-Total Project Cost $200,000
Year 1 $200,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $95,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $10,000 $0 $0 $0 $0 $0 $0
Reserves $95,000 $0 $0 $0 $0 $0 $0
Total 1 $200,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 115
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-47
Department: I Public Works
Capital Project Item: I Carson Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Carson Line- resurface with single coat tar and chip.
Capital Budget -Total Project Cost $160,000
Year 1 $160,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $160,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 160,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�'tunity IsYo��
Year: 12027 1 Capital Item No. PW-48
Department: I Public Works
Capital Project Item: I Baynor Rd.
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Baynor Rd. - single coat tar and chip.
Single coat on adjoining Eden Line.
Capital Budget -Total Project Cost $400,000
Year 1 $400,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $400,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 400,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12027 1 Capital Item No. PW-49
Department: I Public Works
Capital Project Item: I Bogus Rd.
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Bogus Rd. - brush, ditch, culverts, granular and resurface with double coat tar and chip.
Capital Budget -Total Project Cost $80,000
Year 1 $80,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $80,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $80,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-50
Department: I Public Works
Capital Project Item: I Port Burwell Storm Sewer Phase 2
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Storm Sewer Master Plan Phase 2 (Victoria St., Elizabeth St., Wellington St.)
Capital Budget -Total Project Cost $4,680,000
Year 1 $4,680,000 Year 4 $0 1 IYear 7 1 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 IYear 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $4,680,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $4,680,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 180
4,AYHA.1lT
Municipality of Bayham
Capital Information Sheet
OApo+'="unity IsY�Jt�
Year: 12027 1 Capital Item No. PW-51
Department: I Public Works
Capital Project Item: I Communication Tower
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replace Communication Tower at 8354 Plank Rd.
Capital Budget-Total Project Cost $150,000
Year 1 $150,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $75,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $75,000 $0 $0 $0 $0 $0 $0
Total 150,000 0 0 0 0 0 0
Expected Useful Life of the Asset(Years) 130
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-52
Department: I Public Works
Capital Project Item: I Arthur St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Arthur St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $18,000
Year 1 $18,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $18,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $18,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-53
Department: I Public Works
Capital Project Item: I Donnelly Drive
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Donnelly Drive- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $18,000
Year 1 $18,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $18,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $18,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-54
Department: I Public Works
Capital Project Item: I Duke St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Duke St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $18,000
Year 1 $18,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $18,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $18,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-55
Department: I Public Works
Capital Project Item: I East St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
East St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $35,000
Year 1 $35,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $35,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $35,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-56
Department: I Public Works
Capital Project Item: I Elgin St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Elgin St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $18,000
Year 1 $18,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $18,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $18,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-57
Department: I Public Works
Capital Project Item: I Fifth St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Fifth St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $35,000
Year 1 $35,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $35,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $35,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-58
Department: I Public Works
Capital Project Item: I First St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
First St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $55,000
Year 1 $55,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $55,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $55,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-59
Department: I Public Works
Capital Project Item: I Fourth St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Fourth St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $55,000
Year 1 $55,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $55,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $55,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-60
Department: I Public Works
Capital Project Item: I Garner Rd
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Garner Rd - resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $15,000
Year 1 $15,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $15,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $15,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
g,AYHA11?
Municipality of Bayham
Y Capital Information Sheet
oK�APo+.tunity IsY ��
Year: 12028 1 Capital Item No. PW-61
Department: I Public Works
Capital Project Item: I Garnham St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Garnham St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $55,000
Year 1 $55,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $55,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 55,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
g,AYHA11?
Municipality of Bayham
Y Capital Information Sheet
oK�APo+.tunity IsY ��
Year: 12028 1 Capital Item No. PW-62
Department: I Public Works
Capital Project Item: I Hesch St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Hesch St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $18,000
Year 1 $18,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $18,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 18,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-63
Department: I Public Works
Capital Project Item: I Main St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Main St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $110,000
Year 1 $110,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $110,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $110,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
g,AYHA11?
Municipality of Bayham
Y Capital Information Sheet
oK�APo+.tunity IsY ��
Year: 12028 1 Capital Item No. PW-64
Department: I Public Works
Capital Project Item: I Old Chapel St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Old Chapel St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $35,000
Year 1 $35,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $35,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 35,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
g,AYHA11?
Municipality of Bayham
Y Capital Information Sheet
oK�APo+.tunity IsY ��
Year: 12028 1 Capital Item No. PW-65
Department: I Public Works
Capital Project Item: I Second St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Second St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $18,000
Year 1 $18,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $18,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 18,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-66
Department: I Public Works
Capital Project Item: I Sandytown Rd
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Sandytown Rd - resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $200,000
Year 1 $200,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $200,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $200,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-67
Department: I Public Works
Capital Project Item: I Short St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Short St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $18,000
Year 1 $18,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $18,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $18,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-68
Department: I Public Works
Capital Project Item: I Third St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Third St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $70,000
Year 1 $70,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $70,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $70,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-69
Department: I Public Works
Capital Project Item: I Wardwalk St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Wardwalk St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $35,000
Year 1 $35,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $35,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $35,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12028 1 Capital Item No. PW-70
Department: I Public Works
Capital Project Item: I West St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
West St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $70,000
Year 1 $70,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $70,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $70,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12031 Capital Item No. PW-71
Department: I Public Works
Capital Project Item: I Port Burwell Storm Sewer Phase 3
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Storm Sewer Master Plan Phase 3 (Robinson St.)
Capital Budget -Total Project Cost $4,940,000
Year 1 $4,940,000 Year 4 $0 1 IYear 7 1 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 IYear 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $4,940,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $4,940,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 180
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12029 1 Capital Item No. PW-72
Department: I Public Works
Capital Project Item: I Tandem
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replace Truck 9 (2019 Tandem)
Capital Budget -Total Project Cost $570,000
Year 1 $570,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $550,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $20,000 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 570,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 110
g,AYHA11?
Municipality of Bayham
Y Capital Information Sheet
oK�APo+.tunity IsY ��
Year: 12029 1 Capital Item No. PW-73
Department: I Public Works
Capital Project Item: I Brown Rd
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Brown Rd. - resurface with single coat tar and chip.
Capital Budget -Total Project Cost $75,000
Year 1 $75,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $75,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $75,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12029 1 Capital Item No. PW-74
Department: I Public Works
Capital Project Item: I Coyle Rd
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Coyle Rd - resurface with single coat tar and chip.
Capital Budget -Total Project Cost $100,000
Year 1 $100,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $100,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $100,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12029 1 Capital Item No. PW-75
Department: I Public Works
Capital Project Item: I Eden Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Eden Line - brush, ditch, culverts, granular and resurface with double coat tar and chip.
Capital Budget -Total Project Cost $250,000
Year 1 $250,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $250,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $250,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12029 1 Capital Item No. PW-76
Department: I Public Works
Capital Project Item: I Bayham Drive
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Bayham Drive- brush, ditch, culverts, granular and resurface with double coat tar and chip.
Capital Budget -Total Project Cost $350,000
Year 1 $350,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $350,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $350,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12029 1 Capital Item No. PW-77
Department: I Public Works
Capital Project Item: I Travis St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Travis St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $20,000
Year 1 $20,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $20,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $20,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12029 1 Capital Item No. PW-78
Department: I Public Works
Capital Project Item: I Gray St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Gray St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $30,000
Year 1 $30,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $30,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $30,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
4,AYHA1�
Municipality of Bayham
r Capital Information Sheet
�AAot'l'unity IsY�Js�
Year: 12032 1 Capital Item No. PW-79
Department: I Public Works
Capital Project Item: I Port Burwell Storm Sewer Phase 4
Capital Project Priority
Health &Safety Issue Growth Related Need
X Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Storm Sewer Master Plan Phase 4 (Erieus St., Strachan St., Skaespeare St., Newton St., Milton St.)
Capital Budget-Total Project Cost $11,700,000
Year 1 $11,700,000 Year 4 $0 1 IYear 7 1 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 IYear 9 1 $0
Capital u ge -Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $11,700,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 11,700,000 0 0 0 0 0 0
Expected Useful Life of the Asset(Years) 180
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. 1 PW-80
Department: I Public Works
Capital Project Item: I Green Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Green Line. - resurface with single coat tar and chip.
Capital Budget -Total Project Cost $100,000
Year 1 $100,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $100,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $100,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. 1 PW-81
Department: I Public Works
Capital Project Item: I Elliott Rd.
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Elliot Rd. resurface with single coat tar and chip.
Capital Budget -Total Project Cost $50,000
Year 1 $50,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $50,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $50,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-82
Department: I Public Works
Capital Project Item: I Light Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Ditching, brushing, tree removal, replacement of culverts, pulverize surface, add granular material, resurface with
double coat of tar and chip.
Capital Budget -Total Project Cost $3,000,000
Year 1 $3,000,000 Year 4 $0 1 IYear 7 11 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 IYear 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $3,000,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $3,000,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-83
Department: I Public Works
Capital Project Item: I Jackson Line (East)
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Jackson Line Plank Rd - Elgin County Rd. 55 - brush, ditch, culverts, granular and resurface with double coat tar
and chip.
Capital Budget -Total Project Cost $500,000
Year 1 $500,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $500,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $500,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 115
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-84
Department: I Public Works
Capital Project Item: I Ann St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Ann St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $80,000
Year 1 $80,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $80,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $80,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-85
Department: I Public Works
Capital Project Item: I Centre St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Centre St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $160,000
Year 1 $160,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $160,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $160,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-86
Department: I Public Works
Capital Project Item: I Chestnut St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Chestnut St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $50,000
Year 1 $50,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $50,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $50,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-87
Department: I Public Works
Capital Project Item: I Edison Drive
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Edison Drive- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $190,000
Year 1 $190,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $190,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $190,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. 1 PW-88
Department: I Public Works
Capital Project Item: I Elm St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Elm St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $150,000
Year 1 $150,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $150,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $150,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. 1 PW-89
Department: I Public Works
Capital Project Item: I Front St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Front St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $15,000
Year 1 $15,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $15,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $15,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-90
Department: I Public Works
Capital Project Item: I Fulton St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Fulton St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $45,000
Year 1 $45,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $45,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $45,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-91
Department: I Public Works
Capital Project Item: I King St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
King St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $30,000
Year 1 $30,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $30,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $30,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-92
Department: I Public Works
Capital Project Item: I North St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
North St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $65,000
Year 1 $65,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $65,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $65,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-93
Department: I Public Works
Capital Project Item: I Oak St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Oak St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $15,000
Year 1 $15,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $15,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $15,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-94
Department: I Public Works
Capital Project Item: I Old Mill Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Old Mill Line - resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $50,000
Year 1 $50,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $50,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $50,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-95
Department: I Public Works
Capital Project Item: I Otter St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Otter St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $15,000
Year 1 $15,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $15,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $15,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-96
Department: I Public Works
Capital Project Item: I Pearl St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Pearl St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $30,000
Year 1 $30,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $30,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $30,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-97
Department: I Public Works
Capital Project Item: I Pine St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Pine St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $25,000
Year 1 $25,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $25,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $25,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. 1 PW-98
Department: I Public Works
Capital Project Item: I Queen St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Queen St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $15,000
Year 1 $15,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $15,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $15,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-99
Department: I Public Works
Capital Project Item: I Snow St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Snow St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $30,000
Year 1 $30,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $30,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $30,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-100
Department: I Public Works
Capital Project Item: I Soper Rd
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Soper Rd - resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $75,000
Year 1 $75,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $75,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $75,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-101
Department: I Public Works
Capital Project Item: I Union St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Union St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $80,000
Year 1 $80,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $80,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $80,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12030 1 Capital Item No. PW-102
Department: I Public Works
Capital Project Item: I Walnut St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Walnut St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $35,000
Year 1 $35,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 Year 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $35,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $35,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�'tunity IsYo��
Year: 12030 1 Capital Item No. PW-103
Department: I Public Works
Capital Project Item: I Water St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Water St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $15,000
Year 1 $15,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $15,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 15,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
-V,AYHA11?
Municipality of Bayham
Capital Information Sheet
{�APo�.tunity IsYo��
Year: 12033 1 Capital Item No. PW-104
Department: I Public Works
Capital Project Item: I Port Burwell Storm Sewer Phase 5
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Storm Sewer Master Plan Phase 5 (William St., Hannah St., MacNeil Crt., Elizabeth St.)
Capital Budget -Total Project Cost $5,850,000
Year 1 $5,850,000 Year 4 $0 1 IYear 7 1 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 IYear 9 1 $0
Capital Budget- Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $5,850,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $5,850,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 180
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-105
Department: I Public Works
Capital Project Item: I William St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
William St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $16,000
Year 1 $16,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $16,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 16,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-106
Department: I Public Works
Capital Project Item: I Wellington St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Wellington St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $64,000
Year 1 $64,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $64,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 64,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12029 1 Capital Item No. PW-107
Department: I Public Works
Capital Project Item: I Roads Needs Study Update
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Roads Need Study for June 2029
Capital Budget -Total Project Cost $30,000
Year 1 $30,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $30,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 30,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 110
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12035 1 Capital Item No. PW-108
Department: I Public Works
Capital Project Item: I Tunnel Line Culvert removal
Capital Project Priority
x Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Removal of Tunnel Line culvert at rail trail due to deterioration - restore to open ditch - 50% with Tillsonburg
Capital Budget -Total Project Cost $460,000
Year 1 $460,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $460,000 $0 $0 $0 $0 $0 $0
Total 460,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-109
Department: I Public Works
Capital Project Item: I Addison St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Addison St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $96,000
Year 1 $96,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $96,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 96,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 1 Capital Item No. PW-110
Department: I Public Works
Capital Project Item: I Burwell St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Burwell St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $16,000
Year 1 $16,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $16,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 16,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 1 Capital Item No. PW-111
Department: I Public Works
Capital Project Item: I Cowper St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Cowper St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $32,000
Year 1 $32,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $32,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 32,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-112
Department: I Public Works
Capital Project Item: I Elizabeth St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Elizabeth St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $112,000
Year 1 $112,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $112,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 112,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-113
Department: I Public Works
Capital Project Item: I Erieus St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Erieus St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $96,000
Year 1 $96,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $96,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 96,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-114
Department: I Public Works
Capital Project Item: I Hannah St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Hannah St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $16,000
Year 1 $16,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $16,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 16,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-115
Department: I Public Works
Capital Project Item: I Hurley St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Hurley St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $32,000
Year 1 $32,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $32,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 32,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-116
Department: I Public Works
Capital Project Item: I Milton St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Milton St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $48,000
Year 1 $48,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $48,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 48,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-117
Department: I Public Works
Capital Project Item: I Newton St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Newton St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $48,000
Year 1 $48,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $48,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 48,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-118
Department: I Public Works
Capital Project Item: I Pitt St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Pitt St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $112,000
Year 1 $112,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $112,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 112,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 1 Capital Item No. PW-119
Department: I Public Works
Capital Project Item: I Robinson St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Robinson St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $64,000
Year 1 $64,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $64,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 64,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-120
Department: I Public Works
Capital Project Item: I Shakespeare St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Shakespeare St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $80,000
Year 1 $80,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $80,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 80,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-121
Department: I Public Works
Capital Project Item: I Southey St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Southey St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $16,000
Year 1 $16,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $16,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 16,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-122
Department: I Public Works
Capital Project Item: I Strachan St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Strachan St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $64,000
Year 1 $64,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $64,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 64,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-123
Department: I Public Works
Capital Project Item: I Submariners Way
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Submariners Way- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $16,000
Year 1 $16,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $16,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 16,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-124
Department: I Public Works
Capital Project Item: I Tennyson St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Tennyson St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $16,000
Year 1 $16,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $16,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 16,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-125
Department: I Public Works
Capital Project Item: I Victoria St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Victoria St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $32,000
Year 1 $32,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $32,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 32,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12031 Capital Item No. PW-126
Department: I Public Works
Capital Project Item: I Waterloo St
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Waterloo St- resurface with asphalt with curb and gutter.
Capital Budget -Total Project Cost $80,000
Year 1 $80,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $80,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 80,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12033 1 Capital Item No. PW-127
Department: I Public Works
Capital Project Item: I Eden Line from Springer Hill to Culloden Rd.
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
resurface with a single tar and chip
Capital Budget -Total Project Cost $100,000
Year 1 $100,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $100,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 100,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 112
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12033 1 Capital Item No. PW-128
Department: I Public Works
Capital Project Item: I Mitchell Rd from Heritage Line to Jackson Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
resurface with a single tar and chip
Capital Budget -Total Project Cost $110,000
Year 1 $110,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $110,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 110,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 112
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12034 1 Capital Item No. PW-129
Department: I Public Works
Capital Project Item: I Works
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Single Tar& Chip Harmony,Dead End Best,Dead End Green,Dead End Ottergate
Capital Budget-Total Project Cost $60,000
Year 1 $60,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $60,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $60,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 115
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12027 1 Capital Item No. PW-130
Department: I Public Works
Capital Project Item: I James Line
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Single tar and chip
Capital Budget -Total Project Cost $50,000
Year 1 $50,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $50,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 50,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 112
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12034 1 Capital Item No. PW-131
Department: I Public Works
Capital Project Item: I Bridge and Culvert Inspections
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Ontario Structure Inspection Manual (OSIM) Inspections
Capital Budget-Total Project Cost $15,000
Year 1 $15,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $15,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $15,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) I N/A
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12034 1 Capital Item No. PW-132
Department: I Public Works
Capital Project Item: I Sandytown Road Resurface
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Resurface Sandytown Road Asphalt/Curbs Gutter Work Heritage to Stewart
Capital Budget-Total Project Cost $300,000
Year 1 $300,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $300,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $300,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years)
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12034 1 Capital Item No. PW-133
Department: I Public Works
Capital Project Item: I Chapel Street
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Single Tar and Chip North St. to Chute Line
Capital Budget-Total Project Cost $30,000
Year 1 $30,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $30,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $30,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 115
4,AYHA.1Ll
Municipality of Bayham
Capital Information Sheet
OApo+'="unity IsY�Jt�
Year 12026 1 Capital Item No. PW-134
Department: I Public Works
Capital Project Item: I Chute Line Resurface
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Chute Line from Plank road to gravel portion Single Tar&Chip
Capital Budget-Total Project Cost $15,000
Year 1 $15,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $15,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $15,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 125
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12026 1 Capital Item No. PW-135
Department: I Public Works
Capital Project Item: I Climate Risk Assessment- Port Burwell /Vienna Stormwater
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement X Other
escrip ion
Climate risk assessment to support Federal grants for core stormwater infrastructure
Capital Budget -Total Project Cost $85,000
Year 1 $85,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $85,000 $0 $0 $0 $0 $0 $0
Total 1 $85,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 110
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12026 1 Capital Item No. PW-136
Department: I Public Works
Capital Project Item: I Pre-engineering - Port Burwell Stormwater
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement X Other
escrip ion
Allocation for pre-engineering work on the remaining phases of the Port Burwell Drainage Master Plan
Capital Budget -Total Project Cost $35,000
Year 1 $35,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $35,000 $0 $0 $0 $0 $0 $0
Total 35,000 0 0 0 0 0 0
Expected Useful Life of the Asset (Years) 15
Municipality of Bayham
r Capital Information Sheet
�AAorFunily IsY�tlS�
Year: 12026 1 Capital Item No. PW-137
Department: I Public Works
Capital Project Item: I Carson Line
Capital Project Priority
Health &Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Carson Line- brush, ditch, culverts, hill reconstruction -2026-2027 Granular and resurface with double coat tar and
chip. Project started phase 1 in 2025.
Capital Budget-Total Project Cost $600,000
Year 1 $300,000 Year 4 $0 1 IYear 7 1 $0
Year 2 $300,000 Year 5 $0 IYear 8 1 $0
Year 3 $0 Year 6 JYear 9 1 $0
Capital u ge -Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $300,000 $300,000 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 1 $300,0001 $300,00010 0 0 0 0
Expected Useful Life of the Asset(Years) 115
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12029 1 Capital Item No. W-01
Department: I Water
Capital Project Item: I SCADA computer with software and modem
Capital Project Priority
x Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
replacement of the SCADA computer with associated software and modem
Capital Budget-Total Project Cost $28,000
Year 1 $28,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $28,000 $0 $0 $0 $0 $0 $0
Total 1 $28,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 110
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. W-02
Department: I Water Department
Capital Project Item: I Pick Up Truck
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Truck replacements in 2027, 2029, 2031 (Shared with Waste Water)
Capital Budget-Total Project Cost $210,000
Year 1 $66,0001 Year 4 $0 Year 7 $0
Year 2 Year 5 $74,000 Year 8 $0
Year 3 $70,000 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $66,000 $0 $70,000 $0 $74,000 $0 $0
Total 1 $66,000 $0 $70,000 $0 $74,000 $0 $0
Expected Useful Life of the Asset(Years) 110
4,AYHA.1lT
Municipality of Bayham
Capital Information Sheet
OApo+'="unity IsY�Jt�
Year: 12029 1 Capital Item No. W-03
Department: I Water Department
Capital Project Item: I Water Financial Plan
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Water/Wastewater Financial Plan
Capital Budget-Total Project Cost $85,000
Year 1 $40,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $45,000 Year 9 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $40,000 $0 $0 $0 $0 $45,000 $0
Total 40,000 0 0 0 0 45,000 0
Expected Useful Life of the Asset(Years) 15
4,AYHA.1lT
Municipality of Bayham
Capital Information Sheet
OApo+'="unity IsY�Jt�
Year: 12029 1 Capital Item No. W-04
Department: I Water Department
Capital Project Item: I Richmond Well Review
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Richmond Well Review
Capital Budget-Total Project Cost $48,000
Year 1 $23,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $25,000 Year 9 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $23,000 $0 $0 $0 $0 $25,000 $0
Total 23,000 0 0 0 0 25,000 0
Expected Useful Life of the Asset(Years) 15
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12029 1 Capital Item No. W-05
Department: I Water
Upgrades to Vienna Booster Station
Capital Project Priority
x Health & Safety Issue Growth Related Need
x Energy- Environmental Sustainability x Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Replacement of booster pump including associated valves, controls, electrical, SCADA and alarming capabilities
Capital Budget-Total Project Cost $65,000
Year 1 $65,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $65,000 $0 $0 $0 $0 $0 $0
Total 1 $65,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 130
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12029 1 Capital Item No. W-06
Department: I Water
Replacement of water main insulation on the Port Burwell Bridge
Capital Project Priority
Health & Safety Issue Growth Related Need
x Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Replacement of the water main insulation on the Port Burwell bridge
Capital Budget-Total Project Cost $58,000
Year 1 $58,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $58,000 $0 $0 $0 $0 $0 $0
Total 1 $58,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 130
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12030 1 Capital Item No. W-07
Department: I Water
Water Meter Replacement- multi year project (2030 -2031)
Capital Project Priority
Health & Safety Issue Growth Related Need
x Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Replacement of water meters
Capital Budget-Total Project Cost $788,000
Year 1 $388,000 Year 4 $0 Year 7 $0
Year 2 $400,000 Year 5 $0 Year 8 $0
Year 3 $01 Year 6 $0 Year 9 $0
Capital Budget -Financing I Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $388,000 $400,000 $0 $0 $0 $0 $0
Total 1 $388,0001 $400,000 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 125
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12028 1 Capital Item No. W-08
Department: I Water
Bayham water system -fire hydrant rebuilds
Capital Project Priority
x Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Fire hydrant rebuilds
Capital Budget-Total Project Cost $154,000
Year 1 $76,0001 Year 4 $0 Year 7 $0
Year 2 $78,0001 Year 5 $0 Year 8 $0
Year 3 $01 Year 6 $0 Year 9 $0
Capital Budget -Financing I Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $76,000 $78,000 $0 $0 $0
Total 1 $76,0001 $78,000 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 130
g,AYHAIIT
1
Municipality of Bayham
Capital Information Sheet
�PPoi'runily IsY��Kb
Year: 12028 1 Capital Item No. W-09
Department: I Water
Bayham water system-water service line replacement
Capital Project Priority
x Health &Safety Issue Growth Related Need
x Energy- Environmental Sustainability x Service Enhancement
x Efficienc &Effectiveness Accessibility Improvement
x Asset Replacement Other
escrip ion
Replacement of water service lines in the Village of Port Burwell
Capital Budget-Total Project Cost $1,238,000
Year 1 $1,238,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 1 $0
Year 3 $0 Year 6 $0 IYear 9 1 $0
Capital u ge -Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $1,238,000 $0 $0 $0 $0 $0 $0
Total 1,238,000 0 0 0 0 0 0
Expected Useful Life of the Asset(Years) 20-50
�yAYHA.1�
Municipality of Bayham
Capital Information Sheet
Year: 12028 1 Capital Item No. W-10
Department: I Water
Replacement of 7km of transmission water main from the water tower to
Brown Rd -Secondary Water Board ownership
Capital Project Priority
x Health &Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
escrip ion
Replacement of 7km of PVC transmission water main,jointly owned as per the Secondary Water Board. All
associated cost to be shared by Bayham, Malahide and Central Elgin. Project is subject to two outstanding federal
and provincial grant applications.
Capital Budget-Total Project Cost 16,883,000 (Bayham share)
Year 1 $16,883,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital u ge -Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $16,883,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $0 $0 $0 $0 $0
Total 16,883,000 0 0 0 0 0 0
Expected Useful Life of the Asset(Years) 175
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12032 1 Capital Item No. W-11
Department: I Water
water chamber rehabilitation
Capital Project Priority
x Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Rehabilitation of water chambers- isolation valves, structural integrity, water tight, insulate
Capital Budget-Total Project Cost $90,000
Year 1 $32,0001 Year 4 $0 Year 7 $0
Year 2 $33,000 Year 5 $0 Year 8 $0
Year 3 $25,0001 Year 6 $0 Year 9 $0
Capital Budget -Financing I Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $32,000 $33,000 $25,000 $0 $0 $0 $0
Total 1 $32,0001 $33,0001 $25,000 $0 $0 $0 $0
Expected Useful Life of the Asset(Years) 130
4,AYHA.1lT
Municipality of Bayham
Capital Information Sheet
OApo+'="unity IsY�Jt�
Year: 12028 1 Capital Item No. WW-01
Department: I Wastewater Department
Capital Project Item: I System Equipment
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Replacement of Wastewater System Elements
Capital Budget-Total Project Cost $212,000
Year 1 $0 Year 4 $52,000 Year 7 $0
Year 2 $0 Year 5 $54,000 Year 8 $0
Year 3 $51,000 Year 6 $55,000 Year 9 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0 $51,0001 $52,0001 $54,0001 $55,000 $0
Total 0 01 $51,0001 $52,000154,000 55,000 0
Expected Useful Life of the Asset(Years) 110
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12028 1 Capital Item No. WW-02
Department: I Wastewater
Capital Project Item: I SCADA computer replacement- includes software and modem
Capital Project Priority
x Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
SCADA computer replacemet with software and modem located at the wastewater treatment plant
Capital Budget-Total Project Cost $30,000
Year 1 $30,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $30,000 $0 $0 $0 $0 $0 $0
Total 1 $30,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 110
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12026 1 Capital Item No. WW-03
Department: I Wastewater
Wastewater collection system -forcemain air valve rehab
Capital Project Priority
x Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability x Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Wastewater collection system -forcemain air valve rehab.- Eden-Port Burwell
Capital Budget-Total Project Cost $21,000
Year 1 $21,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $21,000 $0 $0 $0 $0 $0 $0
Total 1 $21,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12026 1 Capital Item No. WW-04
Department: I Wastewater
Capital Project Item: I Alarm communication antennas and associated cabling
Capital Project Priority
x Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
replacement of communication antennas and cabling at all wastewater sites
Capital Budget-Total Project Cost $50,000
Year 1 $50,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $50,000 $0 $0 $0 $0 $0 $0
Total 1 $50,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12026 1 Capital Item No. WW-05
Department: I Wastewater
Replacement of wastewater treatment air blowers
Capital Project Priority
Health & Safety Issue Growth Related Need
x Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Replacement of the wastewater treatment air blowers
Capital Budget-Total Project Cost $28,000
Year 1 $28,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $28,000 $0 $0 $0 $0 $0 $0
Total 1 $28,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 125
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12029 1 Capital Item No. WW-06
Department: I Wastewater
Capital Project Item: I SCADA packs - all pump stations and wastewater plant
Capital Project Priority
x Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
replacement of the SCADA packs at all pump stations and wastewater treatment plant-2029-2034
Capital Budget-Total Project Cost $400,000
Year 1 $80,0001 Year 4 $80,000 Year 7 $0
Year 2 $80,0001 Year 5 $80,000 Year 8 $0
Year 3 $80,0001 Year 6 $0 Year 9 $0
Capital Budget -Financing I Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $80,000 $80,000 $80,000 $80,000 $80,000 $0 $0
Total 1 $80,0001 $80,0001 $80,000 $80,0001 $80,000 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12033 1 Capital Item No. WW-07
Department: I Wastewater
Wastewater Collection System -forcemain chamber rehabilitation
Capital Project Priority
x Health & Safety Issue x Growth Related Need
x Energy- Environmental Sustainability x Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Wastewater Colloection System -forcemain chamber rehab. - structural, water tight, isolation valve replacements
(multi year 2033 - 2034 )
Capital Budget-Total Project Cost $211,000
Year 1 $104,000 Year 4 $0 Year 7 $0
Year 2 $107,000 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $104,000 $107,000
Total 1 $104,0001 $107,000 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 130
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12026 1 Capital Item No. WW-08
Department: I Wastewater
Manhole rehabilitation -wastewater collection system
Capital Project Priority
x Health & Safety Issue Growth Related Need
x Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Manhole rehabilitation
Capital Budget-Total Project Cost $271,000
Year 1 $27,0001 Year 4 $29,000 Year 7 $32,000
Year 2 $27,000 Year 5 $30,000 Year 8 $33,000
Year 3 $28,0001 Year 6 $31,000 Year 9 $34,000
Capital Budget -Financing I Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $27,000 $27,000 $28,000 $29,000 $30,000 $31,000 $32,000
Total 1 $27,0001 $27,0001 $28,000 $29,0001 $30,0001 $31,0001 $32,000
Expected Useful Life of the Asset(Years) 25-30
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12028 1 Capital Item No. WW-09
Department: I Wastewater
Wastewater Treatment Plant-ashpalt parking lot upgrade
Capital Project Priority
x Health & Safety Issue Growth Related Need
x Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Ashpalt parking lot upgrade
Capital Budget-Total Project Cost $67,000
Year 1 $67,0001 Year 4 Year 7
Year 2 Year 5 Year 8
Year 3 Year 6 Year 9
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $67,000 $0 $0 $0 $0 $0 $0
Total 1 $67,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 25-30
g,AYHA.1►T
Municipality of Bayham
Capital Information Sheet
�PPoi'tunity Is'YoJK�
Year: 12029 1 Capital Item No. WW-10
Department: I Wastewater
Wastewater Treatment Plant-tendering of plant expansion and
construction
Capital Project Priority
x Health &Safety Issue x Growth Related Need
x Energy- Environmental Sustainability x Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement I Other
escrip ion
Wastewater Treatment Plant-tendering of treatment plant expansion and construction (multi year construction -2029-
2030 )
Capital Budget-Total Project Cost $35,300,000
Year 1 1 $17,389,0001 Year 4 1 Year 7
Year 2 1 $17,911,000 Year 5 Year 8
Year 3 1 1 Year 6 Year 9
Capital u ge -Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $17,389,000 $17,911,000 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves 1 $0 $0
Total 1 $17,389,0001 $17,911,000 $0 0 $0 $0 0
Expected Useful Life of the Asset(Years) 130
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. WW-11
Department: I Wastewater
Wastewater Treatment Plant-eng. and design of plant expansion
Capital Project Priority
x Health & Safety Issue x Growth Related Need
x Energy- Environmental Sustainability x Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Wastewater Treatment Plant- eng. and design of treatment plant expansion
Capital Budget-Total Project Cost $382,000
Year 1 $382,0001 Year 4 Year 7
Year 2 Year 5 Year 8
Year 3 Year 6 Year 9
Capital Budget -Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $382,000 $0 $0 $0 $0 $0 $0
Total 1 $382,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 130
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year 12027 1 Capital Item No. WW-12
Department: I Wastewater
Capital Project Item: I PS#7 and #8 generators
Capital Project Priority
x Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
PS#7 and #8 generator replacements- onsite natural gas powered
Capital Budget-Total Project Cost $150,000
Year 1 $150,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $150,000 $0 $0 $0 $0 $0 $0
Total 1 $150,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 125
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12026 1 Capital Item No. WW-13
Department: I Wastewater
Wastewater Treatment Plant- land acquisition
Capital Project Priority
x Health & Safety Issue x Growth Related Need
x Energy- Environmental Sustainability x Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Wastewater Treatment Plant- land acquisition to accommodate future plant expansions, surveying, land transfer,
associated legal costings
Capital Budget-Total Project Cost $530,000
Year 1 $530,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $530,000 $0 $0 $0 $0 $0 $0
Total 1 $530,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 130
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. WW-14
Department: I Wastewater
Wastewater Treatment Plant- Environmental Assesment
Capital Project Priority
x Health & Safety Issue x Growth Related Need
x Energy- Environmental Sustainability x Service Enhancement
x Efficiency& Effectiveness Accessibility Improvement
x Asset Replacement Other
Description
Wastewater Treatment Plant- EA for plant expansion -tender for eng. firm to complete the EA process
Capital Budget-Total Project Cost $164,000
Year 1 $164,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $164,000 $0 $0 $0 $0 $0 $0
Total 1 $164,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 130
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12028 1 Capital Item No. PR-01
Department: I Parks & Recreation
Capital Project Item: I Replace Quality of Place Banners
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Replace community banners across the entire Municipality
Capital Budget-Total Project Cost $40,000
Year 1 $40,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $40,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $40,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 110
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 2028-2034 1 Capital Item No. PR-02
Department: I Parks & Recreation
Capital Project Item: I Playground Equipment
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness X Accessibility Improvement
X Asset Replacement Other
Description
Improved accessibility for playgrounds (Eden Community Park, Corinth Community Park, Richmond Community
Park, Memorial Park, Straffordville Community Park, Vienna Community Park, Port Burwell Community Park)
Capital Budget-Total Project Cost $630,000
Year 1 $90,0001 Year 4 $90,000 Year 7 $90,000
Year 2 $90,000 Year 5 $90,000 Year 8 $0
Year 3 $90,0001 Year 6 $90,000 Year 9 $0
Capital Budget -Financing I Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $90,000 $90,000 $90,000 $90,000 $90,000 $90,000 $90,000
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $90,0001 $90,0001 $90,000 $90,000 $90,0001 $90,0001 $90,000
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. PR-03
Department: I Parks & Recreation
Capital Project Item: I Beach Shade Structure
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness X Accessibility Improvement
X Asset Replacement Other
Description
Install a permanent beach shade structure over the accessible viewing platform (sun shade sails)
Capital Budget-Total Project Cost $80,000
Year 1 $80,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $80,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $80,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12026 1 Capital Item No. PR-04
Department: I Parks & Recreation
Capital Project Item: I Utility Corridor Repairs
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement X Other
Description
Repair washout/drainage (joint with Tillsonburg)
Capital Budget-Total Project Cost $125,000
Year 1 $125,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $125,000 $0 $0 $0 $0 $0 $0
Total 1 $125,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 125
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12026 1 Capital Item No. PR-05
Department: I Parks & Recreation
Capital Project Item: I Port Burwell Ball Diamond
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Replace Port Burwell Ball Diamond Backstop; upgrade lightning at PB ball diamond
Capital Budget-Total Project Cost $200,000
Year 1 $200,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $65,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $135,000 $0 $0 $0 $0 $0 $0
Total 1 $200,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12029 1 Capital Item No. PR-06
Department: I Parks & Recreation
Capital Project Item: I Electric Charging Station
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Install an electric charging station at the Port Burwell East Beach
Capital Budget-Total Project Cost $20,000
Year 1 $20,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $20,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $20,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 110
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12035 1 Capital Item No. PR-07
Department: I Parks & Recreation
Capital Project Item: I Straffordville &Vienna Memorial Park Pavilions
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Replace roof and fagade steel on the Straffordville and Vienna Memorial Park Pavilions
Capital Budget-Total Project Cost $50,000
Year 1 $50,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $50,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $50,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. PR-08
Department: I Parks & Recreation
Capital Project Item: I Straffordville Ball Diamond
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Upgrade lighting at Straffordville ball diamond
Capital Budget-Total Project Cost $250,000
Year 1 $250,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $75,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $175,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $250,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. PR-09
Department: I Parks & Recreation
Capital Project Item: I Eden Pavilion
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Install a 30' x 40' pavilion in Eden Community Park
Capital Budget-Total Project Cost $100,000
Year 1 $100,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $100,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $100,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. PRA 0
Department: I Parks & Recreation
Capital Project Item: I Richmond Pavilion
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Install a 20' x 30' pavilion in Richmond Community Park
Capital Budget-Total Project Cost $65,000
Year 1 $65,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $65,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $65,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
Municipality of Bayham
of
Capital Information Sheet
�PPol'tunity
Year: 12026 1 Capital Item No. PR-11
Department: Parks & Recreation
Capital Project Item: East Pier Rehabilitation
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
East Pier Rehabilitation (engineering and works)
Capital Budget -Total Project Cost $325,000
Year 1 $50,000 Year 4 $0 Year 7 $0
Year 2 $275,000 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget - Financing Year 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $275,000 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $50,000 $0 $0 $0 $0 $0 $0
Total 1 $50,0001 $275,000 $0 $0 $0 $0 $0
Expected Useful Life of the Asset(Years) 125
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12028 1 Capital Item No. PR-12
Department: I Parks & Recreation
Capital Project Item: I Memorial Park Pavilion
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
Asset Replacement Other
Description
Memorial Park Pavilion size TBD (engineering and construction)
Capital Budget-Total Project Cost $250,000
Year 1 $250,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 Year 6 1 Year 7
Tax Levy $40,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $210,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $250,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 125
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. PRA 3
Department: I Parks & Recreation
Capital Project Item: I Beach Accessibility
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability X Service Enhancement
Efficiency& Effectiveness X Accessibility Improvement
X Asset Replacement Other
Description
Beach Accessibility improvements- mobi-mats
Capital Budget-Total Project Cost $50,000
Year 1 $50,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $50,000 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $50,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12030 1 Capital Item No. FA-01
Department: I Facilities
Capital Project Item: I SCC Parking Lot
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness X Accessibility Improvement
X Asset Replacement Other
Description
Repave the SCC Parking Lot
Capital Budget-Total Project Cost $150,000
Year 1 $150,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $150,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $150,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12026 1 Capital Item No. FA-02
Department: I Facilities
Capital Project Item: I Facility Audits
Capital Project Priority
X Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
X Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Facility Audits of all municipal facilities
Capital Budget-Total Project Cost $60,000
Year 1 $60,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $60,000 $0 $0 $0 $0 $0 $0
Total 1 $60,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 110
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12028 1 Capital Item No. FA-03
Department: I Facilities
Capital Project Item: I Straffordville Library Parking Lot
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness X Accessibility Improvement
X Asset Replacement Other
Description
Repave the Straffordville Library Parking Lot
Capital Budget-Total Project Cost $50,000
Year 1 $50,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $50,000 $0 $0 $0 $0 $0 $0
Total 1 $50,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA�.
Municipality of Bayham
Capital Information Sheet
�pPol.i.unity IsYoJK�
Year: 12026 1 Capital Item No. FA-04
Department: I Facilities
Capital Project Item: I SCC Expansion
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainabilit X Service Enhancement
Efficiency& Effectiveness X Accessibility Improvement
X Asset Replacement Other
escrip ion
SCC Expansion project under ICIP CCR stream
Capital Budget -Total Project Cost $3,614,000
Year 1 $3,614,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget - Financing Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $1,468,000 $0 $0 $0 $0 $0 $0
Other $1,389,000 $0 $0 $0 $0 $0 $0
Reserves 1 $757,000 $0 $0 $0 $0 $0 $0
Total 1 $3,614,000 $0 $0 $0 $0 $0 $0
Expected Useful Life of the Asset (Years) 20-40
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. FA-05
Department: I Facilities
Capital Project Item: I Straffordville Fire Hall Generator Replacement
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Replace Generac generator at Straffordville Fire Hall
Capital Budget-Total Project Cost $60,000
Year 1 $60,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $60,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $60,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 112
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12032 1 Capital Item No. FA-06
Department: I Facilities
Capital Project Item: I PW Generator Replacement
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Replace PW Generator
Capital Budget-Total Project Cost $60,000
Year 1 $60,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $60,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $60,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 112
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12027 1 Capital Item No. FA-07
Department: I Facilities
Capital Project Item: I PW Wash Bay Refurbishment
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Refurbish PW Yard Wash Bay- structural/sandblast/replace steel sheeting
Capital Budget-Total Project Cost $125,000
Year 1 $125,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $125,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $125,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12026 1 Capital Item No. FA-08
Department: I Facilities
Capital Project Item: I Port Burwell Lighthouse
Capital Project Priority
X Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
escrip ion
Restoration - structural, foundation, exterior&engineering/design & contract admin
Capital Budget-Total Project Cost $1,506,250
Year 1 $1,506,250 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $1,506,250 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1,506,250 0 $0 0 0 0 0
Expected Useful Life of the Asset (Years) 140
BAY
Municipality of Bayham
Capital Information Sheet
�APo-runity IsY�Jt�
Year: 12026 1 Capital Item No. FA-09
Department: I Facilities
Capital Project Item: I Port Burwell East Beach Washroom Expansion
Capital Project Priority
Health & Safety Issue X Growth Related Need
X Energy- Environmental Sustainability X Service Enhancement
X Efficiency& Effectiveness X Accessibility Improvement
Asset Replacement Other
escrip ion
Port Burwell East Beach Washroom Expansion
Capital Budget-Total Project Cost $575,000
Year 1 $75,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $500,000 Year 6 $0 Year 9 $0
Capital Budget- Financing Year 1 1 Year 2 Year 3 Year 4 Year 5 Year 6 1 Year 7
Tax Levy $0 $0 $500,000 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $75,000 $0 $0 $0 $0 $0 $0
Total 75,000 0 500,000 0 0 0 0
Expected Useful Life of the Asset (Years) 125
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12028 1 Capital Item No. FA-10
Department: I Facilities
Capital Project Item: I PW Saltdome Cover and Back Bay
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Replace cover-all on PW salt dome and clean/replace/paint steel beams on back bay
Capital Budget-Total Project Cost $100,000
Year 1 $100,000 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 Year 3 1 Year 4 Year 5 1 Year 6 Year 7
Tax Levy $100,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $100,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12026 1 Capital Item No. FA-11
Department: I Facilities
Capital Project Item: I Marine Museum Library Parking Lot
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness X Accessibility Improvement
X Asset Replacement Other
Description
Repave the Marine Museum Parking Lot
Capital Budget-Total Project Cost $75,000
Year 1 $75,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $75,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $75,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12032 1 Capital Item No. FA-12
Department: I Facilities
Capital Project Item: I SCC Generator Replacement
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Replace SCC Generator
Capital Budget-Total Project Cost $70,000
Year 1 $70,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $70,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $70,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 112
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12031 Capital Item No. FA-13
Department: I Facilities
Capital Project Item: I Port Burwell Library Roof Replacement
Capital Project Priority
Health & Safety Issue Growth Related Need
X Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Upgrade roof to sheet steel
Capital Budget-Total Project Cost $25,000
Year 1 $25,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $25,000 $0 $0 $0 $0 $0 $0
Total 1 $25,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 150
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12029 1 Capital Item No. FA-14
Department: I Facilities
Capital Project Item: I Straffordville Library Accessible Ramp
Capital Project Priority
X Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
Repair ramp edging, replace railing, etc.
Capital Budget-Total Project Cost $25,000
Year 1 $25,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $25,000 $0 $0 $0 $0 $0 $0
Total 1 $25,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 120
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12035 1 Capital Item No. PD-01
Department: I Planning
Capital Project Item: I Official Plan Comprehensive Review
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
5-year Comprehensive Official Plan Review- 2 year project completion in 2036
Capital Budget-Total Project Cost $65,000
Year 1 $45,0001 Year 4 $0 Year 7 $0
Year 2 $20,000 Year 5 $0 Year 8 $0
Year 3 $01 Year 6 $0 Year 9 $0
Capital Budget -Financing I Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $45,000 $20,000 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $45,0001 $20,000 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 15
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12026 1 Capital Item No. PD-02
Department: I Planning
Capital Project Item: I Zoning By-law Comprehensive Review
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
10-year Comprehensive Zoning By-law Review- 2 year project completion in 2027
Capital Budget-Total Project Cost $70,000
Year 1 $45,0001 Year 4 $0 Year 7 $0
Year 2 $25,000 Year 5 $0 Year 8 $0
Year 3 $01 Year 6 $0 Year 9 $0
Capital Budget -Financing I Year 1 1 Year 2 1 Year 3 1 Year 4 1 Year 5 1 Year 6 1 Year 7
Tax Levy $0 $25,000 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $45,000 $0 $0 $0 $0 $0 $0
Total 1 $45,0001 $25,000 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 15
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12030 1 Capital Item No. PD-03
Department: I Planning
Capital Project Item: I Official Plan 5 Year Review
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
5-year Official Plan Review-2 year project completion in 2031
Capital Budget-Total Project Cost $55,000
Year 1 $40,0001 Year 4 $0 Year 7 $0
Year 2 $15,000 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 1 Year 6 1 Year 7
Tax Levy $40,000 $15,000 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $40,0001 $15,000 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 15
g,AYHA.II?
Municipality of Bayham
Capital Information Sheet
tunity Is'`loJS�
Year: 12032 1 Capital Item No. PD-04
Department: I Planning
Capital Project Item: I 5-year Zoning By-law Review
Capital Project Priority
Health & Safety Issue Growth Related Need
Energy- Environmental Sustainability Service Enhancement
Efficiency& Effectiveness Accessibility Improvement
X Asset Replacement Other
Description
5-year Zoning By-law Review- 1 year project completion in 2032
Capital Budget-Total Project Cost $35,000
Year 1 $35,0001 Year 4 $0 Year 7 $0
Year 2 $0 Year 5 $0 Year 8 $0
Year 3 $0 Year 6 $0 Year 9 $0
Capital Budget -Financing Year 1 1 Year 2 1 Year 3 1 Year 4 Year 5 Year 6 1 Year 7
Tax Levy $35,000 $0 $0 $0 $0 $0 $0
Development Charges $0 $0 $0 $0 $0 $0 $0
Grants $0 $0 $0 $0 $0 $0 $0
Other $0 $0 $0 $0 $0 $0 $0
Reserves $0 $0 $0 $0 $0 $0 $0
Total 1 $35,000 $0 $0 $0 0 $0 $0
Expected Useful Life of the Asset(Years) 15